Planning and Estimating Flashcards
What is the official contract drawing that you will mark on during construction to show the actual as built conditions?
Red lined
When a construction project is completed, what type of drawing must be submitted to ROICC?
As built
What type of plan shows the spot where a building is to be placed on a piece of land?
Site plan
To find the size and placement of reinforcing steel in the grade beam for a building, you should look in what main division of the drawings?
Structural division
Which of the following divisions should contain the environmental pollution controls?
Civil
Specifications from which of the following sources, combined with drawings, define the project in detail and show exactly how is to be constructed?
Project specifications
Whenever there is conflicting information between the drawings and project specs, the specifications take the precedence over the drawings.
True
The construction standards institute (CSI) has organized the format of specifications into 16 construction divisions, but NAVFAC has added a 17th division. What is that division?
Expeditionary structures
In most NCF projects, construction activities should not be less than 6 days in duration.
False
What section of the project package contains the Bill of materials?
Three
The work schedule of a battalion for one person per week is based on an average of how many hours?
55
In an NMCB, what is the normal duration of a workday, in hours, to and from the job site?
9
NAVFAC P-405, Seabee planner and estimates handbook defines a man day as how many hours per day?
8
What type of estimate are the basis for purchasing materials, determining equipment, and determining manpower requirements?
Activity
Master activities are usually assigned to the project’s by what authority?
NCRs
Which of the following activities is NOT an activity that would be listed on a master activities list for a typical building project?
Paint
What NAVFAC publication lists the number of man goes to accomplish one unit of work?
P-405
The man day capability equation is used to calculate the duration of a construction activity.
True
For planning purposes, what authority assigns an availability factor to an NMCB?
Naval construction brigade