Planning an agile Project Part 1 Flashcards
Creating your project charter section
what should agile charter accomplish and how pages should it be
A .P. L. E. P
An Agile Charter should be an agreement and not a plan. It should list what every party wants from the project.
1 page
Creating your project charter section
What are the 3 main sections of an agile Charter?
V,M,S
vision, mission and success criteria.
Creating your project charter section
What is the project’s mission and provide an example?
E DAV
CCETP WSLS
The project’s mission is what everyone will do to accomplish the vision.
Create a cutting-edge technology platform “that combines a website, a smartphone application, “and location awareness to help our customers “identify local birds.”
Creating your project charter section
What does the project vision answer and example?
D,P
HPE LWP
why are we doing this project
A good vision statement for the bird finder application might be, “help people enjoy the outdoors “and learn more about the wonderful birds “that live on our planet.”
Creating your project charter section
What is the success criteria within the project charter and provide an example?
one
10,000, 100,000 GEO
These will be the simple, one sentence tests to make sure that the project accomplished its mission.
10,000 users within three months of the initial version. Sign up 100,000 users in the first year. Get endorsed by a major ornithology website
Using Relative estimating
What is relative estimating?
C.DK vs DK
TW HC
Relative estimating compares what you don’t know against what you do know. You might not be able to guess how much a truck weighs, but if you saw the truck, you can probably guess how many cars equal a truck.
Using Relative estimating
What are the reasons Agile uses relative estimating?
FCP
CEC
The first reason is that it takes away from the false comfort of precision.
The second reason Agile uses relative estimating is that it keeps the team from confusing estimates from commitments.
An estimate is a best guess. A commitment is often a worst case scenario.
Using Relative estimating
What is the advantage of relative estimation?
KPAP
IGW
D
Relative estimation is a key part of adapting over planning. There’s always limited time in a project. A relative estimate allows you to immediately get into the work. It keeps your project from spending too much time debating how long a task will take