PJM - Objective 2.1 Flashcards

1
Q

Net fee determined by subtracting consultants’ fees from the gross fee for the project.

A

Net Service Revenue (NSR)
Net Revenue

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Labor hours and dollar amounts planned at project initiation.

A

Planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Labor hours and dollar amounts spent as of a current date.

A

Job- to Date (JTD)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Labor hours and dollar amounts estimated from current date to project completion.
*Single most important factor used in project tracking and monitoring for project success.

A

Estimate -to-Complete (ETC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

JTD plus ETC labor hours and dollar amount estimated at project completion.

A

Estimate-at-Completion (EAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Over/Under calculation indicating labor hours and dollar amounts at project completion relative to planned estimates

A

Planned Estimate at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Current work in place for the project, phase, or task, expressed as a subjective percent complete and not based on the percentage of labor or dollar amounts

A

Percent Complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

(Direct Labor + Overhead)/ Direct Labor

A

Break Even (multiplier)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Overhead/Direct Labor

A

Overhead (multiplier)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Current subjective percent complete/ Direct Labor

A

Effective Multiplier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Firm wide standard target multiplier, including profit target

A

Target

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Net Service Revenue (NSR)/Planned Cost

A

Planned Multiplier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Total NSR/EAC labor dollars

A

Estimate at Completion (EAC) Multiplier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Amount billed to client based on contract compensation amounts and percent complete.

A

Billed/invoiced amounts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Revenue recognized in the accrual accounting system based on subjective percent complete X net service revenue

A

Earned Revenue Amounts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Amounts billed to the client but not recognized as earned revenue in the accrual accounting system

A

Billed-not-Earned (BNE)

17
Q

Amounts recognized as earned revenue in the accrual accounting system but not billed to the client.

A

Earned-not-Billed (ENB)

18
Q

What two multipliers are used to see where the project is now, where it is projected to be at the end of the project, and what needs to be adjusted to bring the project back within budget?

A

1.) Effective Multiplier
2.) Est. at Completion (EAC) Multiplier

19
Q

Raw labor costs determined from bottom-up Project Work Plan

A

Planned Labor

20
Q

Raw labor costs expended on the project from the start date to the current date

A

Job to Date Labor (JTD)

21
Q

Raw labor costs estimated to be expended on the project from the current date to the project completion date.

A

Estimate-to-Complete Labor (ETC)

22
Q

The sum of JTD labor and ETC labor

A

EAC Labor (estimate-at-Completion)

23
Q

The Planned Labor Costs - (minus) the EAC Labor costs.

A positive amount projects less labor will be used at the end of the project than planned, resulting in a multiplier and profit above the target. Project is in good standing!

A negative number projects a multiplier and profit below target. Project is in serious trouble!

A

Planned - (minus) AEC

Compensation / Planned Cost = Planned Multiplier

24
Q

Project Work Planning

A

1.) Is key to establishing project budgets,
2.) determining schedules to perform the work,
3.) monitoring the progress as the project moves forward
4.) is essential to a firm’s success and must be supported by management.