PCM-PJM-CE- A201- General Questions Flashcards
To learn the content of A201 General Conditions
According to A.I.A. Document A - 201, a contractor who is delayed by unanticipated poor weather conditions in progressing with the job may request an extension of time, placed in writing to the architect, within ___________ days after commencement of the delay.
A. 10 days
B. 15 days
C. 21 days
D. 30 days
C. 21 days
see: 15.1.3.1
According to A.I.A. Document A - 201, certificates of insurance filed with the owner by the contractor cannot be cancelled without _____________ prior written notice to the owner.
A. 10 days
B. 14 days
C. 21 days
D. 30 days
D. 30 days
see: ????
According to A.I.A. Document A - 201, should concealed conditions encountered in the performance of the work below the surface of the ground be substantially different from those ordinarily encountered, notice must be given within _______________ days after the first observance of the conditions.
A. 7 days
B. 10 days
C. 14 days
D. 21 days
C. 14 days
see: 3.7.4
According to A.I.A. Document A - 201, if the work should be stopped for a period of 30 days by the contractor because the architect has not issued a certificate for payment, then the contractor may, upon an additional _____________ written notice to the owner and the architect, terminate the contract and recover from the owner payment for all work executed.
A. 7 days
B. 10 days
C. 14 days
D. 21 days
A. 7 days
see 14.1.4
According to A.I.A. Document A -201, the contractor shall confine operations at the site to which of the following:
A. Areas permitted by ordinance.
B. Areas permitted by permits and contracts.
C. Area permitted by law.
D. All of the above.
D. All of the above.
See. 3.13 use of site
According to A.I.A. Document A - 201, if the work has been covered by the contactor which the architect had not specifically requested to observe prior to its covering, the architect may request that the work be uncovered and _______________.
A. The cost is borne by the contractor.
B. That if such work be found in accordance with the contract documents, cost shall be charged to the owner.
C. That if such work is found not in accordance with the contract documents, the cost shall be charged to the contractor.
D. Both B and C.
D. Both B and C.
see 12.1.1
According to A.I.A. Document A -201, “shop drawings” are drawings, diagrams, schedules and other data specifically prepared for the work by the _______________.
A. Contractor (only)
B. Contractor or any sub-contractor (only)
C. Architect (only)
D. Contractor or any sub-contractor, manufacturer, supplier or distributor (only)
D. Contractor or any sub-contractor, manufacturer, supplier or distributor (only)
See. 3.12.1
According to A.I.A. Document A - 201, a change order is a written order to the ___________, signed by the _____________, issued after execution of the contract, authorizing a change in the work or an adjustment in the contract sum or the contract time.
A. owner / contractor and architect
B. architect I contractor
C. contractor / owner and architect
D. contractor / owner
C. contractor / owner and architect
See 7.2.1
According to A.I.A. Document A - 201, if a contractor is judged to be bankrupt, then the owner can terminate the employment of the contractor after giving ___________ days notice.
A. 4 days
B. 5 days
C. 6 days
D. 7 days
D. 7 days
See 14.2.2
According to Document A - 201, no portion of the work requiring submission of a shop drawing, product data, or sample shall be commenced until _______________.
A. Three working days after the submissions approval.
B. Four working days after the submissions approval.
C. Five working days after the submissions approval.
D. The submission has been approved by the architect.
D. The submission has been approved by the architect.
See 3.12.7
According to A.I.A. Document A - 201, the acceptance of final payment shall constitute___________.
A. A waiver of all claims by the owner.
B. A waiver of all claims by the contractor except those discovered within seven days after payment.
C. A waiver of all claims by the contractor except those made in writing and still unsettled.
D. A waiver of all claims by the contractor.
C. A waiver of all claims by the contractor except those made in writing and still unsettled.
See 9.10.5
According to A.I.A. Document A – 201, a certificate for payment is issued by the ____________.
A. Architect to the owner
B. Architect to the contractor
C. Contractor to the architect
D. Contractor to the owner
A. Architect to the owner
See 9.4.1
According to A.I.A. Document A - 201, the contractor shall submit to the architect an itemized application for payment at least _____________ days before the date for each progress payment established in the owner - contractor agreement.
A. 7 days
B. 10 days
C. 12 days
D. 14 days
B. 10 days
See 9.3.1
According to A.I.A. Document A - 201, _________ is required to furnish all surveys describing the physical characteristics, legal limits and utility locations for the site of the project.
A. The owner
B. The architect
C. The contractor
D. A surveyor hired by the architect
A. The owner
See 2.3.4
With certain exceptions, A.I.A. Document A - 201 states that all claims, disputes and other matters in question involving the contract are to be settled by ____________.
A. Mediation
B. Arbitration
C. The circuit court judge (no jury) in the county in which the dispute takes place
D. The National Labor Relations Board
A. Mediation
See 15.3.1
According to A.I.A. Document A - 201, after receipt of the contractor’s application for payment, the architect will, __________ within days, either issue a certificate for payment to the owner, or notify the contractor in writing his reasons for withholding the certificate.
A. 7 days
B. 10 days
C. 14 days
D. 21 days
A. 7 days
See 9.4.1
According to A.I.A. Document A -201, the contractor must supply evidence of the quality of equipment and materials ______________.
A. On all items exceeding $800.00 in value.
B. Upon completion of the job.
C. Only for those items specified in the contract
D. Upon request by the architect
D. Upon request by the architect
see 3.5.1
According to A.I.A. Document A - 201, the contractor shall at all times ________________.
A. Enforce strict discipline among his employees
B. Maintain good order among his employees
C. Not employ anyone not skilled in the task assigned to him/her
D. All of the above
D. All of the above
see 3.4.3
According to A.I.A. Document A - 201, monies not paid when due to either party of the contract shall ___________.
A. Bear interest at the legal rate.
B. Be held in escrow by the owner for arbitration.
C. Because to immediately cease construction activity.
D. All of the above
A. Bear interest at the legal rate.
See 13.5
According to A.I.A. Document A -201, the architect’s approval of shop drawings or samples shall ______________.
A. Relieve the contractor from responsibility of deviations of shop drawings if the architect is informed in writing.
B. Relieve the contractor from responsibility or errors in the shop drawings.
C. Allow the contractor to continue the work started as per the shop drawings.
D. Not allow deviations by the contractor, but the contractor may co*Atm.
C. Allow the contractor to continue the work started as per the shop drawings.
See 3.12.7
According to A.I.A. Document A - 201, the responsibility: signing building permits belongs to the _____________.
A. Owner
B. Contractor
C. Architect
D. Realtor
B. Contractor
See 3.7.1
According to A.I.A. Document A - 201, the contractor shall be responsible to the owner for the acts and omissions for all ______________.
A. Of his employees
B. Subcontractors
C. Persons performing any work under the contract
D. All of the above
D. All of the above
See 3.3.2
According to A.I.A. Document A - 201, the contract time may be extended for which of the following reasons?
A. Lack of funds to complete the job on time.
B. Accidents by workers.
C. Authorized by owner pending arbitration.
D. Employee negligence
C. Authorized by owner pending arbitration.
see: 8.3.1
According to A.I.A. Document A - 201, the contractor must maintain at the building site a copy of ____________.
A. Change orders
B. Shop drawings
C. Any addenda
D. All of the above
D. All of the above
see 8.3.1