PCM-PJM-CE- A201- General Questions Flashcards
To learn the content of A201 General Conditions
According to A.I.A. Document A - 201, a contractor who is delayed by unanticipated poor weather conditions in progressing with the job may request an extension of time, placed in writing to the architect, within ___________ days after commencement of the delay.
A. 10 days
B. 15 days
C. 21 days
D. 30 days
C. 21 days
see: 15.1.3.1
According to A.I.A. Document A - 201, certificates of insurance filed with the owner by the contractor cannot be cancelled without _____________ prior written notice to the owner.
A. 10 days
B. 14 days
C. 21 days
D. 30 days
D. 30 days
see: ????
According to A.I.A. Document A - 201, should concealed conditions encountered in the performance of the work below the surface of the ground be substantially different from those ordinarily encountered, notice must be given within _______________ days after the first observance of the conditions.
A. 7 days
B. 10 days
C. 14 days
D. 21 days
C. 14 days
see: 3.7.4
According to A.I.A. Document A - 201, if the work should be stopped for a period of 30 days by the contractor because the architect has not issued a certificate for payment, then the contractor may, upon an additional _____________ written notice to the owner and the architect, terminate the contract and recover from the owner payment for all work executed.
A. 7 days
B. 10 days
C. 14 days
D. 21 days
A. 7 days
see 14.1.4
According to A.I.A. Document A -201, the contractor shall confine operations at the site to which of the following:
A. Areas permitted by ordinance.
B. Areas permitted by permits and contracts.
C. Area permitted by law.
D. All of the above.
D. All of the above.
See. 3.13 use of site
According to A.I.A. Document A - 201, if the work has been covered by the contactor which the architect had not specifically requested to observe prior to its covering, the architect may request that the work be uncovered and _______________.
A. The cost is borne by the contractor.
B. That if such work be found in accordance with the contract documents, cost shall be charged to the owner.
C. That if such work is found not in accordance with the contract documents, the cost shall be charged to the contractor.
D. Both B and C.
D. Both B and C.
see 12.1.1
According to A.I.A. Document A -201, “shop drawings” are drawings, diagrams, schedules and other data specifically prepared for the work by the _______________.
A. Contractor (only)
B. Contractor or any sub-contractor (only)
C. Architect (only)
D. Contractor or any sub-contractor, manufacturer, supplier or distributor (only)
D. Contractor or any sub-contractor, manufacturer, supplier or distributor (only)
See. 3.12.1
According to A.I.A. Document A - 201, a change order is a written order to the ___________, signed by the _____________, issued after execution of the contract, authorizing a change in the work or an adjustment in the contract sum or the contract time.
A. owner / contractor and architect
B. architect I contractor
C. contractor / owner and architect
D. contractor / owner
C. contractor / owner and architect
See 7.2.1
According to A.I.A. Document A - 201, if a contractor is judged to be bankrupt, then the owner can terminate the employment of the contractor after giving ___________ days notice.
A. 4 days
B. 5 days
C. 6 days
D. 7 days
D. 7 days
See 14.2.2
According to Document A - 201, no portion of the work requiring submission of a shop drawing, product data, or sample shall be commenced until _______________.
A. Three working days after the submissions approval.
B. Four working days after the submissions approval.
C. Five working days after the submissions approval.
D. The submission has been approved by the architect.
D. The submission has been approved by the architect.
See 3.12.7
According to A.I.A. Document A - 201, the acceptance of final payment shall constitute___________.
A. A waiver of all claims by the owner.
B. A waiver of all claims by the contractor except those discovered within seven days after payment.
C. A waiver of all claims by the contractor except those made in writing and still unsettled.
D. A waiver of all claims by the contractor.
C. A waiver of all claims by the contractor except those made in writing and still unsettled.
See 9.10.5
According to A.I.A. Document A – 201, a certificate for payment is issued by the ____________.
A. Architect to the owner
B. Architect to the contractor
C. Contractor to the architect
D. Contractor to the owner
A. Architect to the owner
See 9.4.1
According to A.I.A. Document A - 201, the contractor shall submit to the architect an itemized application for payment at least _____________ days before the date for each progress payment established in the owner - contractor agreement.
A. 7 days
B. 10 days
C. 12 days
D. 14 days
B. 10 days
See 9.3.1
According to A.I.A. Document A - 201, _________ is required to furnish all surveys describing the physical characteristics, legal limits and utility locations for the site of the project.
A. The owner
B. The architect
C. The contractor
D. A surveyor hired by the architect
A. The owner
See 2.3.4
With certain exceptions, A.I.A. Document A - 201 states that all claims, disputes and other matters in question involving the contract are to be settled by ____________.
A. Mediation
B. Arbitration
C. The circuit court judge (no jury) in the county in which the dispute takes place
D. The National Labor Relations Board
A. Mediation
See 15.3.1
According to A.I.A. Document A - 201, after receipt of the contractor’s application for payment, the architect will, __________ within days, either issue a certificate for payment to the owner, or notify the contractor in writing his reasons for withholding the certificate.
A. 7 days
B. 10 days
C. 14 days
D. 21 days
A. 7 days
See 9.4.1
According to A.I.A. Document A -201, the contractor must supply evidence of the quality of equipment and materials ______________.
A. On all items exceeding $800.00 in value.
B. Upon completion of the job.
C. Only for those items specified in the contract
D. Upon request by the architect
D. Upon request by the architect
see 3.5.1
According to A.I.A. Document A - 201, the contractor shall at all times ________________.
A. Enforce strict discipline among his employees
B. Maintain good order among his employees
C. Not employ anyone not skilled in the task assigned to him/her
D. All of the above
D. All of the above
see 3.4.3
According to A.I.A. Document A - 201, monies not paid when due to either party of the contract shall ___________.
A. Bear interest at the legal rate.
B. Be held in escrow by the owner for arbitration.
C. Because to immediately cease construction activity.
D. All of the above
A. Bear interest at the legal rate.
See 13.5
According to A.I.A. Document A -201, the architect’s approval of shop drawings or samples shall ______________.
A. Relieve the contractor from responsibility of deviations of shop drawings if the architect is informed in writing.
B. Relieve the contractor from responsibility or errors in the shop drawings.
C. Allow the contractor to continue the work started as per the shop drawings.
D. Not allow deviations by the contractor, but the contractor may co*Atm.
C. Allow the contractor to continue the work started as per the shop drawings.
See 3.12.7
According to A.I.A. Document A - 201, the responsibility: signing building permits belongs to the _____________.
A. Owner
B. Contractor
C. Architect
D. Realtor
B. Contractor
See 3.7.1
According to A.I.A. Document A - 201, the contractor shall be responsible to the owner for the acts and omissions for all ______________.
A. Of his employees
B. Subcontractors
C. Persons performing any work under the contract
D. All of the above
D. All of the above
See 3.3.2
According to A.I.A. Document A - 201, the contract time may be extended for which of the following reasons?
A. Lack of funds to complete the job on time.
B. Accidents by workers.
C. Authorized by owner pending arbitration.
D. Employee negligence
C. Authorized by owner pending arbitration.
see: 8.3.1
According to A.I.A. Document A - 201, the contractor must maintain at the building site a copy of ____________.
A. Change orders
B. Shop drawings
C. Any addenda
D. All of the above
D. All of the above
see 8.3.1
Which of the following statements is INCORRECT as related to A.I.A. Document A - 201?
A. The contractor shall secure and pay for all permits.
B. The contractor shall secure and pay for all governmental licenses necessary for the execution and completion of the work, which are applicable at the time the bids are received.
C. The contractor shall be responsible for ascertaining that the drawings and specifications are applicable to all laws and statutes.
D. The contractor shall pay all government fees necessary for the execution and completion of the work.
C. The contractor shall be responsible for ascertaining that the drawings and specifications are applicable to all laws and statutes.
see 3.2.3, 3.7.1
According to A.I.A. Document A -201, which of the following statements is true?
A. The contractor shall not be responsible for any cutting or patching that may be required to complete his work.
B. The contractor is not responsible for damage to work or other contractors while performing his work.
C. Any costs caused by defective of ill-timed work shall be borne by the party responsible, therefore.
D. If a contractor unintentionally damages the work of another contractor, he is not responsible for its correction.
C. Any costs caused by defective of ill-timed work shall be borne by the party responsible, therefore.
see 3.5.1
According to A.I.A. Document A -201, all permits, governmental fees and licenses necessary for the proper execution in the completion of the project shall be secured by the
A. Owner
B. Contractor
C. Architect
D. None of the above
B. Contractor
See 3.7.1
Given: The use of a utility easement is required to reach the rear of a large construction site. According to A.I.A. Document A - 201, the ___________ shall secure permission to use such an easement.
A. Architect
B. Owner
C. Subcontractor
D. Contractor
B. Owner
see 2.3.1
According to A.I.A. Document A - 201, the ____________ is to furnish the site survey.
A. Architect
B. Owner
C. Subcontractor
D. Contractor
B. Owner
see 2.3.4
According to A.I.A. Document A – 201, which of the following may be issued by the architect alone?
A. Either a construction change directive or a change order
B. A change order only
C. An order for a minor change in the work (only)
D. A construction change directive (only)
C. An order for a minor change in the work (only)
see 7.4
According to A.I.A. Document A - 201, if the contractor fails to carry out the work in accordance with the contract documents, before proceeding to make good any deficiencies, the owner must ____________.
A. Notify the contractor three days prior to proceeding.
B. Have the architects’ approval and have notified the contractor in writing twice.
C. Have the architects’ approval only.
D. Notify the building official only.
B. Have the architects’ approval and have notified the contractor in writing twice.
see 2.5, 2.4
According to A.I.A. Document A - 201, the subcontractor has the same responsibilities and obligations to the contractor as the _______________.
A. Architect has to the owner,
B. Owner has to the contractor
C. Contractor has to the architect and owner
D. Owner has to the architect and contractor
C. Contractor has to the architect and owner
see 5.3
According to A.I.A. Document A - 201, the DOES NOT have to maintain one record copy of the _____________ at the construction site.
A. Drawings
B. Contract between the owner and contractor
C. Specifications
D. Change orders
B. Contract between the owner and contractor
see 3.11
Given: On May 1, the contractor submitted the application for certificate for payment number 2 for a construction project in the amount of $32,969.00, for approval to the project architect. The project architect, through no fault of the contractor, had not issued the certificate of payment by May 12.
According to A.I.A. Document A - 201, the contractor may, upon __________ additional days after written notice to the owner and the architect, stop the work on the project until payment of the amount owing the contractor is received.
A. 5 days
B. 7 days
C. 10 days
D. 14 days
B. 7 days
see 9.7
Given: On May 1, the contactor the submitted application and certificate for payment number 3 for a shopping center in the amount of $44,969.00 for approval to the project architect. The architect, through no fault of the contractor, had not issued the certificate of payment by May 11.
According to A.I.A. Document A - 201, the contractor may, upon ___________ additional days after written notice to the owner and the architect, stop work on the project until payment in the amount of $44,969.00 has been received.
A. 5 days
B. 7 days
C. 10 days
D. 14 days
B. 7 days
see 9.7
According to A.I.A. Document A - 201, a contractor has the same responsibilities and obligations to the subcontractor as the _______________.
A. Architect has to the subcontractor
B. Contract has to the owner
C. Architect has to the contractor
D. Contractor has to the architect
C. Architect has to the contractor
see 5.3
Given: An emergency arose in which a contractor, while protecting the owner’s property, incurred costs that were not part of the original contract According to A.I.A. Document A - 201, the contractor has _____________ days of the emergency to notify the architect if the contractor wishes to make a claim for an increase in the contract sum.
A. within 7 days
B. within 21 days
C. within 30 days
D. within 60 days
B. within 21 days
see 15.1.3.1
According to A.I.A. Document A - 201, which of the following would NOT be allowed by the architect when determining an adjustment to the contract was due to a change directive?
A. Costs of transporting materials
B. Costs of bond premium adjustments
C. Costs of labor fringe benefits
D. Rental costs for hand tools
D. Rental costs for hand tools
see 7.3.4
According to AIA 201, who owns the plans?
A. owner
B. contractor
C. architect
D. building department
C. architect
see ???
According to AIA 201, the contractor shall notify the owner/architect within _______ days if hidden or unforeseen work is encountered.
A.7
B.10
C.14
D.5
C.14
See 3.7.4
If an easement is to be secured for construction access, according to AIA 201, the _________secures and pays for it.
A. contractor
B. owner
C. architect
D. Building Official
B. owner
According to AIA 201, who will prepare the change orders?
A. owner
B. architect
C. contractor
D. all of above
B. architect
According to AIA 201, the contractor should keep ___________ set(s) of plans at the jobsite.
A. one
B. two
C. three
D. number prescribe by architect
A. one
According to AIA 201, the __________is responsible for correcting the plans
A. engineer
B. contractor
C. architect
D. owner
C. architect
According to AIA 201, a contractor that is delayed by unanticipated poor weather conditions may request an extension of time by notifying the architect in writing, within___________, after commencement of the delay.
A. 5
B. 12
C. 21
D. 30
C. 21
see 15.1.3.1
According to AIA 201, all permits, governmental fees and licenses necessary for the proper execution in the completion of a project shall be secured by the____________.
A. Architect
B. Contractor
C. Owner
D. Building Official
B. Contractor
According to AIA 201 a change order is a written order to the_______ , signed by the_________ ,issued after execution of the contract, authorizing a change in the work or an adjustment in the contract sum or contract time.
A. Owner / contractor & architect
B. architect / contractor
C. contractor / owner & architect
D. contractor / owner
C. contractor / owner & architect
According to AIA 201, the responsibility for securing building permits belongs to the ___________.
A. Architect
B. Contractor
C. Owner
D. Building Official
B. Contractor
The contractor must utilize a utility easement to reach the rear of the construction site. According to AIA 201 the______shall secure permission to use the easement.
A. Architect
B. Contractor
C. Owner
D. Utility Subcontractor
C. Owner
According to AIA 201, when a project is complete, who owns the plans?
A. contractor
B. owner
C. architect
D. engineer
C. architect
A contractor does not agree with the method of adjustment for a change in the contract and the Architect determines the amount to be paid. The Architect determines expenses to include: labor and fringes at $1,000, equipment at $550, materials at $750, hand tools at $100 and additional supervision at $200. In accordance with AIA 201, the Architect will authorize payment in the amount of ________.
A. $2,600
B. $1,000
C. $2,500
D. $0
C. $2,500
According to AIA 201, the architect must notify the contractor in writing whether or not the owner or Architect has reasonable objection to the use of a subcontractor______.
A. within 14 days
B. within 21 days
C. in accordance with the schedule requirements
D. promptly
A. within 14 days
see 5.2.1
According to AIA Document A201, the contract documents consist of the agreement between _______________.
A. owner & subcontractor
B. subcontractor & contractor
C. owner, contractor & subcontractor
D. contractor & owner
D. contractor & owner
see 1.1.1
The contract documents shall be signed by the ________________ as provided in the agreement.
A. contractor & owner
B. owner, contractor & subcontractor
C. architect & contractor
D. architect & owner
A. contractor & owner
see 1.5.1
The __________ shall furnish surveys describing physical characteristics, legal limitations and utility locations for the site of the project and a legal description of the site.
A. owner
B. contractor
C. architect
D. engineer
A. owner
see. 2.2.3
According to AIA Document A201, the ____________ is responsible for securing and paying for all necessary easements on a construction project.
A. contractor
B. architect
C. owner
D. engineer
C. owner
see 2.2.2
According to AIA Document A201, the owner is not responsible for which of the following:
A. assessment fees
B. permits & fees
C. easements
D. utility locations
B. permits & fees
see 2.2.2