PERT/CPM Flashcards

1
Q

Defines the working and non-working days of a project.

A

Project calendar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Acronyms of PERT

A

Program Evaluation and Review Technique

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Acronyms of CPM

A

Critical Path Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

a statistical tool used in project management, which was designed to analyze
and represent the tasks involved in completing a given project.

A

PERT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

technique where you identify tasks that are necessary for project completion
and determine scheduling flexibilities

A

CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

the longest sequence of activities that must be finished on time in order for the
entire project to be complete

A

CPM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Activities which could be done at the same time.

A

Parallel Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Activities which could not be done at the same time or activities which should be done one after the other.

A

Sequential Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

the earliest possible point in time on which the uncompleted portions of an activity can START, based on the network logic and any schedule constraints.

A

Early start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

the earliest possible point in time on which the uncompleted portions of an activity can FINISH, based on the network logic and any schedule constraints

A

Early Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

the latest possible point in time that an activity can begin without delaying a specified milestone

A

Late start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

represents the latest date an activity can finish, without delaying the finish of the project.

A

Late Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The longest path in the network.
It is also where slack is minimum

A

Critical Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

is the amount of waiting time between two tasks.Or in other words, ______ is the amount of time by which a successor activity will be delayed.

A

Lag

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

can be used in all the four logical relationships in scheduling, such as Finish-to-start (FS), start-to-start
(SS), finish-to-finish (FS) and start-to-finish (SF)

A

Lag

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

is the amount of time that a successor activity can
start before the completion of a predecessor activity

A

Negative Lag