PERT Flashcards

1
Q

EITHER START OR END OF AN ACTIVITY

A

PERT EVENT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EVENTS THAT EITHER
IMMEDIATELY PRECEDES OR SUCCEED ANOTHER EVENT. ALL EVENTS
NEED TO BE COMPLETED IN SEQUENCE.

A

PREDESSOR OR SUCCESSOR EVENT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

THE PERFORMING OF A TASK, RECORDED BY THE TIME
TAKEN TO DO SO AND THE RESOURCES REQUIRED.

A

PERT ACTIVITY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

HE BREAKING-DOWN OF ACTIVITIES WITHIN AN
ACTIVITY.

A

PERT SUB-ACTIVITY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

THE MINIMUM TIME REQUIRED TO COMPLETE AN
ACTIVITY.

A

OPTIMISTIC TIME

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

THE MINIMUM TIME REQUIRED TO COMPLETE AN
ACTIVITY.

A

OPTIMISTIC TIME

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

IT REPRESENTS THE LONGEST ESTIMATED TIME PERIOD
WITHIN WHICH A TASK IS LIKELY TO BE COMPLETED.

A

PESSIMISTIC TIME

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

HE COMPLETION TIME HAVING THE HIGHEST
PROBILITY

A

MOST LIKELY TIME

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

IS A PRE-ESTIMATED TIME WITHIN WHICH THE PROJECT IS
SUPPOSED TO GET COMPLETED

A

EXPECTED TIME

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

THE EXCESS TIME AVAILABLE FOR AN ACTIVITY WHERE THINGS CAN
TAKE LONGER THAN PLANNED WITHOUT CAUSING DELAYS

A

SLACK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

THE LONGEST POSSIBLE ROUTE FROM START TO FINISH,
REPRESENTING THE TOTAL TIME ALLOTTED, SO ANY DELAYS BEYOND THIS
WILL MEAN THE PROJECT HAS RUN LATE

A

CRITICAL PATH

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Activity - Description- Immediate Predecessors - Time Estimate

A

Activity List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In pert it is an activity which is represented by an arrow

A

branch or arc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

In the beginning and end of each activity a circle that is called _____ is placed.

A

Node

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The term_____ is also used in connection with the nodes.

A

Event

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

each letter(A,B,C) is inside of each node

A

AON

17
Q

each letter(A,B,C) is at the branch or arc

A

AOA