Performing the Job Flashcards
Obligations of the Contractor to the Owner
- Duty to complete the work
- Implied term that they will perform work diligently and in good and workmanlike manner
Duty to complete the work
Contractor has the duty to complete the work in accordance with the contract, its drawings, plans, and other documents
Performance both obligation and right meaning
Owner not able to perform any part of the contractor’s scope of work without breaching the contract
Party of duty to complete work is implied duty that
that the owner will not do anything to prevent or hinder the contractor in its performance of the work
Owner/ design pro does not owe a duty of care to….
advise contractor on how to perform the work
When will obligation to complete extend?
If generally contemplated in the anticipated scope
Implied terms for contractors under duty to complete
- That work will be performed in good workmanlike manner (implies fitness in some cases)
- Work will comply with building regulations
Performance is ____ to payment
Condition precedent
whether full performance depends on the contract
Partial performance will not entitle partial payment when
owner does not benefit from anything other than full performance
Breaches that absolve the owner of obligation to pay
Those that go to the root of the contract
Substantial Performance
achieved where there is remaining work but the work remaining does not go to the root of the contract (case by case basis)
What happens at substantial performance?
Owner required to pay contract price (unless contract says due on total completion)
Entitlement to be paid for sub performance different when
Residential as well as if there is unique design or aesthetic preferences
Time for completion
Duty to complete means complete at a specified time (usually completion time in contract expressed in milestones or date)
Time at large contracts
Contract without timeframe
Time at large times calculated
Reasonable amount of time (fact dependant inquiry)
Contracts that do stipulate can be time at large
If owner interferes
Cases where contractor’s actions caused concurrent delay
- Ex: owner preventing access to site but contractor falling behind as well
- Contract may still be considered time at large
3 kinds of delay
1) Excusable delay
2) Compensable delay
3) Non-compensable delay
Excusable delay
- delays for which neither party is responsible (ex: force major)
- may justify schedule extensions but not compensation
Compensable delay
- delay caused by an act or omission of the owner (ex: impeding access)
- Compensation to contractor and schedule extensions
Non-compensable delay
- delay caused by contractor’s own failure to perform its duties
- Contractor may be liable for damages
- Contractor may have to do additional work without pay
Owner obligation
- Not to impede/ provide sufficient access to site and materials
- Payment
- Not to interfere with contractors work
- Get permits, easements, and rights of servitude
- In D-B-B appropriate, timely, and sufficiently appropriate drawings
Owner obligation not to impede creates what implied terms?
- implied term that site will be handed over to the contractor within a reasonable time after signing the contract
- implied term that specified documents will be supplied at an appropriate time
- where owner responsible for material implied obligation to supply those materials in the stipulated form and at an appropriate time to allow contractor to meet schedule
What if owner breaches obligation not to impede
Required to pay costs to contractor resulting from breach
Increased duty to supply materials when schedule is tight
failure to supply items that would have just been an inconvenience tight schedule can up this from a nuisance to a significant breach
Compensable delay damages
Contractor can claim for:
- Some recovery for offsite overhead costs
- Loss of profit earning capacity
- Specific on sight overhead costs for legitimate period of extension
Compensable delay damages not awarded
Where caused by contractors failure to mitigate