Performance Domain Artifact - Baseline Artifacts Flashcards
Budget
Baseline Artifacts - The approved estimate for the project or any work breakdown structure (WBS) component or any schedule activity.
PLANNING PROJECT MEASURMENT
Milestone Schedule
Baseline Artifacts - A type of schedule that presents milestones with planned dates.
DEV PLANNING PROJECT MEASUREMENT
Performance Measurement Baseline (PMB)
Baseline Artifacts - Integrated scope, schedule, and cost baselines used
for comparison to manage, measure, and control project execution.
PLANNING PROECT DELVERY MEASUREMENT
Project Schedule
Baseline Artifacts - An output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources.
PLANNING PROJECT MEASURMENT
Scope Baseline
Baseline Artifacts - The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary that can be changed using formal change control procedures and is used as the basis for comparison to actual results.
PLANNING PROECT DELVERY MEASUREMENT