Performance and Breach Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

What are the different ways to discharge a contract?

A
  • Agreement
  • Performance
  • Breach
  • Frustration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Explain discharge by agreement

What is said about expressing this agreement?

A

Discharge by agreement sees a contract being terminated by the parties agreeing to release each other from their obligations

It is said that if there is no express form of agreement parties may be found to have abandoned their rights

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the two requirements for a contract to be discharged by performance?

A
  • Performance must be precise and exact (this rule is strictly applied by the courts)
  • Must comply with contractual description
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the developments in the law?

A
  • Consumer rights Act 2015: s11 - Goods has to be as described (ss 1 & 2)
  • Sale of Goods Act 1979 :
  • s13 - Sale by description, s14 - Implied terms as to quality and fitness (ss 2), s15 - Sale by sample
  • Unfair Contract Terms Act [1977]
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Give case law examples for compliance with contractual description?

Refer to table of cases for answers on what the cases were specifically about

A
  • Re Moore & Co v Launder & Co [1921] (Authority) - canned fruit case
  • *There was a contract for the sale of cases of Austrialian canned fruits
  • Goods were stated as being: a) in cases containing 30 tins each b) Payment to be per dozen tins
  • Sellers tendered the whole quantity ordered but : about hald of the cases contained 24 tins and the rest contained 30 tins
  • It thus did not reflect on what they agreed
  • Buyers refused to take the delivery on this ground
  • Held: Buyers were entitled to reject goods as they were not as described in contract*
  • Arcos v EA Ronaasen [1933] (key case) -
  • *Seller agreed to sell vertical posts (staves) of Russian redwood and whitewood
  • Seller knew buyer was going to use for a making cement barrels
  • Agreement contained stipulations as to length bredth and thickenness
  • Some variation allowed to length and bredth but NOT to thickness
  • Buyer rejected goods on arrival : a) Did not conform to description in contract b) Thickness specified in the contract was half an inceh but on arrival the staves were 9/16th of an inch - so was not precise and exact and the measurement was not right
  • Held: Buyers not bounf to accept goods and entitled to demand goods to comply with descrioption in contract, even though the goods tendered were merchantable

JC Smith’s textbook states that it is unclear if the same result will be reached today because
1. In Reardon Smith Line ltd V Hansen Tangen Lord Wilberforce said that some of the prior case law had been too technical
2. A new section was inserted into the Sale of Goods Act in 1994 which provided that where the buyer is not a consumer and ‘the breach is so slight that it would be unreasonable for him to reject the [goods]’ the breach is not to be treatef as a breach of condition but may be treated as if it were a breach of warranty. Section 15 A applies to the terms implied by sections 14 and 15 as well as section 13

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the less strictly applied rule in compliance with contractual description? And what were modifications in the law as a result?

Can still be regarded a key case as it has legislation to back it up

A

*Reardon Smith Line Ltd v Hansen Tangen [1976]
**
Agreement made before building a vessel commenced that vessel to be chartered on completion
* Vessel was to be built at Osaka with the yard/hull number 354 but due to its size the vessel was built at Oshima and had the yard/hull number of Oshima 004
* But in all external documents it was known
* a) BUT in all external documents it was “known as” or “called” Osaka 354
* b) HOWEVER physical attributed of vessel corresponded with requirements of respectibve charters - corresponded with the terms of the contract
* * When vessel was ready for delivery in 1974, an oil crisis caused market collapse and charterers tried to escape obligation by rejecting vessel, arguing that, by analogy with contracts for the sale of goods:

* a) the vessel tendered did not correspond with contractual description;
b) vessel was Oshima 004 and not Osaka 354
c) It was stamped 004 and not Osake 354 *
* *Held: Vessel did comply with the description set out in the respective charters, fundamentally the physical attributes comply with the description - change of name not that important

* Lord Wilberforce stated that:
* * Prior case law regarding sale by description was too technical
* Failure to comply with description, however trivial, would amount to a breach of condition and entitle a buyer to reject the goods, leading to harsh results
* Need to establish a term was a condition as a matter of interpretation, before it can be established as a condition under s 13, Sale of Goods Act 1893, and as amended in 1979
Since Reardon Smith: - modifications to legislation
* New s15A inserted into Sale of Goods Act in 1994
* A new section was inserted into the Sale of Goods Act in 1994 which provided that where the buyer is not a consumer and ‘the breach is so slight that it would be unreasonable for him to reject the [goods]’ the breach is not to be treatef as a breach of condition but may be treated as if it were a breach of warranty. Section 15 A applies to the terms implied by sections 14 and 15 as well as section 13

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the general rule of “entire obligation” v partial performance ?

A

Where the bilateral contract stipulates an entire piece of work is to be done by one party, that obligation must be completely performed, unless the parties agreed other wise

  • Cannot recover payment for partial performance of an entire obligation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Give case law examples for “entire obligation” v partial performance

A

Cutter v Powell [1775-1802] 101 ER 573
* The contractual note stated:
“Ten days after the ship Governor Parry arrives at Liverpool, myself master, I promise to pay to Mr. T. Cutter the sum of thirty guineas, provided he proceeds, continues and does his duty as second mate in the said ship from hence to the port of Liverpool. Kingston, July 31st, 1793”
* Mr. T. Cutter performed his duties under the contract until his death which happened BEFORE the ship arrived at Liverpool.
* Could his widow recover his wages?

Held:
* Wages were not recoverable
* Cutter had not completed performance of the contract - he died before he ship could be delivered

Ashurst J :
“This is a written contract, and it speaks for itself.
And as it is entire, and as the defendant’s promise depends on a condition precedent to be performed by the other party, the condition must be performed before the other party is entitled to receive any thing under it.”

The same principles were applied in Appleby v Myers [1867] to a contract to install machinery in the defendant’s premises. The bulk of the work was done when, without the fault of either party, the premises were burnt down and the machinery destroyed. The claimant could not recover anything.

Look at information regarding Section 30 of the Sale of Goods Act and if the defendant has an option to accept or reject the claimant’s incomplete performance and the claimant chooses to accept the courts will infer a new contract

Sumpter v Hedges (1898)
* Claimant was a builder, who contracted to erect certain buildings on defendant’s land for a lump sum of £565
* After he had done PART of the work, he abandoned the contract (when the sum reached £333) because he ran into financial difficulties - he had received part of the price but his action to recover the balance of the value of the work he had done failed
* Defendant then completed the buildings using materials left by the claimant on the site. The defendant was held liable to pay for the materials, because he had an option whether to use them. This was different from the work done by the claimant.

Held:
* The court held that the defendant had no option to accept or reject an unfinished building on his land, so was not liable to pay anything for the work done. The unfinished building was simply there on the land and could not be rejected. Moreover, the defendant was bound not to leave it in an incomplete state.

  • Claim for a quantum meruit (ie: for what one has earned) for partial performance should fail

Bolton v Mahadeva [1972]
* Bolton installed central heating for £560 in Mahadeva’s house
* It was too cold: heat came unevenly and heater gave off fumes - therefore the heating (core of the contract did not work)
* Bolton refused to correct it, which would cost Mahadeva an extra £174
* Mahadeva refused to pay any money at all

Held:
* Bolton was not entitled to payment as there had been no substantial performance of the contract, as per the “entire obligation” rule - (would have been a central heating that works completely and not from time to time)
* The lack of performance was not a trivial one, rather it went to the root of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Substantial performance? Support answer with case law

A

Substantial performance is if there is a minor variation from the contractual terms, the other party cannot claim no discharge

There may be rise to an action for damages if there is a breach of contract

Hoenig v Issacs [1952]

  • Contract by claimant to decorate and furnish defendant’s flat for £750
  • Defendant alleged workmanship was poor and defective and only paid £400
  • Claimant sued for the balance

Held:

a) Court of Appeal found that the contract was an ordinary lump sum contract that had been substantially performed

b) Although there were some defects, they were valued at £55 (minor defects), so balance owed was £750 less £55

Where there is substantial performance the claimant may still be entitled to the complete lump sum but defected or troublesome areas may be deducted from this lump sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Give case law examples of Performance having to be ON TIME

What do these cases show about the expression of goods needing to be done at a certain time?

A

Startup v Macdonald (1843)

  • Defendant contracted to buy 10 tons of linseed oil from Plaintiff at a certain price
  • Parties agreed oil “to be free delivered by the plaintiffs to the defendant within the last fourteen days of March, and paid for at the expiration of that time in cash”
  • Goods were tendered on the last of the fourteen days at 21h
  • Buyer refused to accept owing to the lateness of hour

Held:
Although it was late at night, the goods were still tendered within the agreed period (ie: during the last fourteen days of March) - they did not make it clear that there was a specific time during this period for the goods to be tendered

This case shows that there needs to be an express statement of goods are to be brought at a specific time

United Scientific Holdings Ltd & Burnley Borough Council [1978]

  • Rent review provisions in two leases
  • In each case, failure to strictly adhere to timetable established by the rent review clauses
  • Tenants claimed time was of the essence under the timetable, so landlord had lost right to a review

Held

House of Lords pointed out that time is not of the essence for performance of contractual obligations UNLESS the express words of the contract, the nature of the subject matter or the surrounding circumstances indicated to the contrary - There may be some timetable but if it is not expressly said at the time, it does not count

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is NON-performance?

A

NON-performance is when obligations have not been discharged in full and thus the conract comes to an end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Quantum Meruit?

A

Payment of what they have done/earned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a case law example of Quantum meruit?

A

Planche v Colburn (1831) EWHC KB J56

  • Defendants were in the process of compiling a series of books to be entitled ‘the juvenile library’
  • They engaged the claimant to write a book on medieval costume and amour
  • When claimant had written several chapters, the series was cancelled
  • Publishers offered to publish the book separately

Held

Claimant was entitled to refuse publishers’ offer and claim in quantum meruit for work completed on the book

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When is there a breach in a contract?

A

If the terms of a contract have or have not been complied with and also depends on the term:

  • Condition (core of the contract)
  • Warranty (lesser term in the contract)
  • Inominate term

Whether a party has breached a contract by faulty or inadequate performance will depend on the standard of performance required (sometimes implied by things such as legislation)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When will a breach give rise to termination?

What legal rights cannot be ignored?

A

If the contract prives a right to terminate for the breach in question
OR
The law provides a right to terminate for the breach in question

Some legal rights cannot be ignored such as the Consumer Rights Act 2015

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When is there a contractual right and a legal right to terminate a contract?

A

Contractual right: If the contract confers a right to terminate for any breach

Legal right will always exist: if there is a breach of an essential term (condition)
and
Legal right may exist where : there is a serious breach of an inominate or intermediate term - what is the nature of the breach and has the creach caused serious loss?

17
Q

What are the actions an affected party can take when a condidtion of a contract has been broken?

A

The affected party has right to terminate the contract and claim damages

18
Q

What are the actions an affected party can take when a warranty of a contract has been broken?

A

The affected party can get damages only

19
Q

What are the actions an affected party can take when an inomminate term of a contract has been broken?

A

The affected party has the right to damages and potentially a right to to terminate depending on the nature and the effect of the breach

20
Q

What is key case demonstrates the inability to terminate a contract as it **does not **go to the heart of the contract?

What did Lord Diplock say concerning this?

A

Honkong Fir Shipping v Kawasaki Kiesen Kaisha

  • HFS agreed to charter a ship to KKK
  • Clause 3 of the charter agreement provided that the shipowners should ‘maintain her in a thoroughly efficient state in hull and machinery during service’
  • The machinery broke down on several occasions and this caused significant delays
  • KKK terminated the agreement because of the delay
  • HFS argued that KKK was not legally entitled to terminate the contract
  • HFS sought damages for wrongful termination by KKK

Held:
1. If defaulting part is able to do substantially what they promised, then the injured party has no right to terminate the contract
2. BUT if the breach deprived them of substantially the whole benefit they expected to receive, then they may refuse to proceed with the contract - How much of the contract are you allowed to receive? ;
a) Have to look a the nature of the breach and its affect on performance before deciding if the breach is serious enough for the injured party to terminate
* The “unseaworthiness” related to the defective state of the ship’s engines and the inefficiency of the engine room staff
* This resulted in 5 week’s delay and a further 15 weeks for repairs
* BUT, even at the end of all this time, the injured party (the charterparty) still had 20 months left on its charter agreement - had almost two years of use of the ship to go, may pay for the amount of time they could not use it but 20 weeks is minute compared to almost two years left

  • Per Lord Diplock, the breach did not deprive the charters of “substantially the whole benefit of the contract and they were not entitled to terminate from the breach”
21
Q

What are the different types of breach?

A
  • Actual Breach
  • Anticipatory Breach
  • Unjustified/Mistaken termination
22
Q

What is the definition of Actual breach?

A

Breach that has already occurred because one of the parties has refused to fulfil their contractual obligations or have sone so incompletely or improperly

  • Clear to identify
  • Breach of condition goes to the heart of the conract
23
Q

What is the definition of anticipatory breach and what can the injured party do?

A

Before the performance is due, a party either renounces the contract or disables itself from performing the contract (breaching before the contract even starts)

The injured party can treat the contract as ended and bring action for damages
OR
Affirm the contract and continue to demand performance until final date of perfomance

24
Q

What are some case law examples showing anticipatory breach?

A

Hochster v De La Tour (1853) 2 E & B 678
* The defendants entered into a contract in April to employ the claimant in June as a courier for a trip around Europe
* In May, the defendant wrote to the claimant stating that he no longer required its services
* The claimant brought an action for breach of contract prior to the date on which he was supposed to start work
* The defendant argued there could be no breach before 1 June
Held:

There was an anticipatory breach of a contractual obligation that could not be properly performed when due after agreeing that performance and date. Anticipating that you are not going to perform the contract that you have agreed to .

Frost v Knight (1871-72) L.R. 7 Ex. 111
* The defendant promised to marry the plaintiff as soon as his (defendant’s) father died
* During the father’s lifetime, however, the defendant broke off the engagement

Held:

  • Hochster v De la Tour could be applied - an anticipatory breach of contract had been committed (since the father had not yet died) and the plaintiff was entitled to sue
  • No difference between situation where time for performance was a particular day OR time for performance depended on a contingency, such as the death of the father
25
Q

What is the case that saw the ability for an affected party to ignore the repudiation or the anticipatory breach of the other party?

What was said in obiter?

A

White and Carter (Councils) Ltd v McGregor [1961] (H/L decision; (Scottish case)) - key cases because of the reasoning
* A garage proprietor, by his agent, agreed with an advertising contractor for the display of advertisements in Scotland for his garage for three years.
* One of the terms was that a fee was payable weekly and if any payment was four weeks in arrears, the whole three years’ payments should immediately become payable.
* On the day the contract was entered into, the proprietor immediately cancelled the contract (an anticipatory breach).
* Contractor refused to accept cancellation and displayed advertisements in accordance with the contract and when first payment was four weeks overdue, sued for the whole three years’ payments.

Under Scottish law: if one party to a contract repudiates it, the other is at liberty to perform it, if they can do so without the co-operation of the repudiating party. If so, they can insist on the repudiating party paying in full the amount due under the contract and are not obliged to accept the repudiation. This is also the case in English law

(HOL) Held:
* The contractor was not seeking damages but payment and the consideration but for services rendered - so what they did was valid

Obiter - Lord Reid thought it contrary to equitable principles and public policy for a claimant to be permitted to ignore an anticipatory breach and perform their obligations, in order to sue for the agreed sum. - But this way had been done for years in common law so he had to allow it

26
Q

What was the distinguished case that went against the general rule of the affected party being able to accept or reject the repudiation of another party?

A

**Clea Shipping v Bulk Oil, The Alaskan Trader (No.2) [1938] **
* Parties entered into a contract for a 2-year charter of a ship
* After 1 year, the vessel suffered a serious engine breakdown which it was clear would take several months to repair
* Charterers informed the owner that in those circumstances they had no further use for the vessel, in repudiation of the contract
* BUT: owner still proceeded with the necessary repairs, which amounted to £800,000 and after its completion the owners had informed the charterers that the vessel was once again fit for service, but the charterers refused to give the master any orders
* The owners refused to accept this conduct as repudiation of the contract and kept the vessel at readiness, fully crewed.

**Held: (distinguished from White and Carter) **
* That the general rule is that the innocent party in a repudiation may elect to accept or reject the repudiation as he pleases. But the courts can limit this in exceptional cases
* This was the case here where the arbitrator had found that the owners had no legitimate interest in continuing to perform the contract and should have accepted the charterers repudiation within 24 hours of the vessel being ready for service. Accordingly the charterers would not be liable for hire, but they would be liable in damage
* The courts therefore did not allow them to ignore the repudiation

27
Q

What is the 3 layerd question to identify anticipatory breach?

A

Can a victim of an anticipatory breach who:

  • is able to perform their part of the contract
  • without the cooperation of the other party
  • simply ignore the anticipatory breach, fulfil their own contractual obligation and claim the consideration promised?
28
Q

What happned in the case Woodar Investment Ltd v Wimpey Construction (UK) Ltd? Why was the judgement surprising?

A

Woodar Investment Development Ltd v Wimpey Construction (UK) Ltd [1980]

  • Wimpey contracted to buy land for £850,000 and agreed to pay £150,000 on completion to a third party, Transworld Trade Ltd
  • The contract allowed the purchaser to rescind the contract if, before completion, a statutory authority E.g council) ‘shall have commenced’ to acquire the property by compulsory purchased
  • On date contract was entered into, both parties knew that a draft compulsory purchase order had been made
  • Wimpey misconstrued the contract and thought the specified circumstances (compulsory purchase) had arisen, when they had not (as only a draft order had been made)
  • Wimpey tried to terminate relying on the contractual provision and Woodar sought damages alleging that this amounted to a wrongful (ie: an unjustified) repudiation

Held:
* Majority in the House of Lords found that Wimpey had misconstrued the contract by thinking the specified circumstances had arisen
* BUT…there was no evidence that they intended to repudiate the contract or refuse future performance if the issue as to the right to rescind was decided against them
○ If they had found that in fact there was no evidence that this clause was going to run they would have going with the deal - if there was a mistake they would have kept on going
○ The intention was not that if Wimpey made a mistake they were going to repudiate the contract; they thought that was what was happening, that there was going to be a compulsory purchase, they would have continued and because Wimpey declared this intention not to repudiate after the HoL told them they made a mistake - HoL found that there was no breach
* No anticipatory breach found ,surprisingly because it really appeared to Woodar that Wimpey was repudiating the contract
This was surpising because in the earlier case of Federal Commerce Navigation Co Ltd v Molena Alpha Inc, it was found that it is still anticiaptory breach even if the party is mistaken

29
Q

Where is the preferred judgment for unjustified/mistaken repudiation? Who said this judgment?

A

The preferred judgement was found in Federal Commerce Navigation Co Ltd v Molena Alpha Inc where Lord Denning stated : ‘I have yet to learn that a party who breaks a contract can excuse himself by saying that he did it on the advice of his lawyers; or that he was under an honest misapprehension. Nor can he excuse himself on those grounds from the consequences of a repudiation’.

30
Q

What case led to the development in the Sale of Goods Act 1979?

A

Reardon Smith Line Ltd v Hansen Tangen [1976]

31
Q

Explain the principle of accord and satisfaction and the case where it came from

A

“The accord is the agreement by which the obligation is discharged. The satisfaction is the consideration which makes the agreement operative” - Scrutton LJ ** in British Russian Gazette and Trade Outlook Ltd. V. Associated newspapers Ltd. [1933] **