Perform Integrated Change Control Flashcards
Monitoring and Controlling
What is the purpose of the Perform Integrated Change Control process?
To review all change requests, get approval or rejection of such changes, and update appropriate information in light of any changes.
What is the correct sequence of steps to follow in the Perform Integrated Change Control Process?
1) Identify change, 2) Evaluate impact of change, 3) Issue change request, 4) Get approval for change, 5) Update change request log and project documents, 6) Communicate change to stakeholders and get buy in, 7) Direct and manage work according to the new plan.
What is a change log?
Document changes that occur during a project.
What is Change Control Board (CCB)?
Responsible for meeting and reviewing the change requests and approving or rejecting.
What are the outputs of the Perform Integrated Change Control process?
Approved Change Requests, Change Log, Project Documents Updates, Project Management Plan Updates
What are the inputs of the Perform Integrated Change Control process?
Project Management Plan, Work Performance Reports, Change Requests, EEFs, OPAs
What are the tools or techniques of the Perform Integrated Change Control process?
Expert Judging, Meetings, Change Control Tools