Close Project or Phase Flashcards
Closing
What is the purpose of the Close Project process?
To finalize all activities across all of the project management process groups to formally complete the project or phase
What is the correct sequence of events in the Closing Process?
1) Gain Formal Acceptance, 2) Document Lessons Learned, 3) Archive Records, 4) Close Contract, 5) Release Team, and 6) Close Project or Phase
What should be your primary guide when closing a project or phase?
Project Management Plan
You are managing a project that has not gone well, and you have been informed by the sponsor that the project is terminated. How should you proceed?
Stop all work, gather and organize all documentation, and release the project team.