Past Boards Objective Questions Flashcards
- Every construction project shall have a suitable______. Which must be in accordance with these rules,
and other orders and issuances issued by the DOLE.
Construction Safety and Health Program
- The process of injecting any agent into soil or rock to increase its strength or stability, protect foundations or reduce ground water.
Grouting
- An increase in soil density of a cohesive soil resulting from the expulsion of water from the soil’s void spaces.
Consolidation
- measure of materials ability to resist indentation or penetration.
Hardness
- The elements to consider when planning National Roads
a. Limited frontage access
b. Development set well back from the highway.
c. All access to premises provided via provincial roads
d. Number of intersections to be minimized.
e. Suitable at grade-channelized intersections for minor flows and other elements.
f. No roadside vendors.
- Which of the following is the correct step by step process of finishing standard weight concrete slabs chronological order?
- Bleeding
- Screeding
- Leveling
- Edging
- Jointing
- Floating
- Troweling
- Broom Finishing
- The basic lane width appropriate for national road.
3.35 meters
- The berth structure projecting out from the shoreline.
Pier
- Signs used to guide drivers through a change in horizontal alignment of the Road.
Chevron Signs
- What are the capacity requirement for all scaffoldings?
Atleast 4 times its own weight
- operating a motor vehicle on a street or highway can be complex and demanding at times, but it can be boring at other times. these range of circumstances coupled with the range of driver capabilities presents a challenge to the highway designer. it is helpful to begin by considering the three essential elements such as navigation, guidance and control is referred to as:
Driving Task
- A method of protecting employees from cave-ins from material that could fall or roll from an excavation face or into an excavation or collapse of adjacent structures. This includes support systems, sloping and benching systems, shield systems and other systems that provide the necessary protection.
Protective System
- The bucket volume contained within the bucket when following the outline of the bucket sides is referred to as:
Plate line capacity
Signs that inform road users about the direction and distances of destinations on the route they are following or along other roads that intersect their route
Guide Signs
- It provides the detailed requirements for the materials, equipment, and workmanship to be incorporated into the project.
Specifications
- If you are preparing a report on PERT CPM network in a construction job, what time scheduling should you consider in the preparation of the PERT CPM network diagram ?
a. Pessimistic Time
b. Optimistic Time
c. All of the above
d. Probable Time
All of the above
- It is a measure of a material’s ability to dissipate or deaden mechanical vibrations.
Damping Capacity
- This drawing has elevation as its vertical axis and horizontal distance as measured along the center line of
the facility (or other reference line), as its horizontal axis.
Profile
- A formal or legally binding agreement between two parties is referred to as :
Contract
- It is an informal group discussion that focuses on a particular safety issue. These can be used daily to
promote department safety culture as well as to facilitate health and safety discussions on job sites is
known as :
Toolbox meeting
- It occurs after the completion of construction, and the resolution of the majority of punch list and
commissioning issues.
Profile
- Because concrete is unable to maintain a particular shape before it sets. It must be placed in a form or mold. In building construction, this is called
Formwork
- A method of protecting workers from cave-ins by excavating the sides of an excavation to form one or a series of horizontal level or steps, usually with a vertical or near vertical surfaces between levels.
Benching
- The safe capacity of piles driven by powered hammers is based on the following data :
a. Average penetration per blow, last 6 blows
b. Energy of Hammer
c. Weight of Hammer
d. Weight of Pile including appurtenances
e. Coefficient of restitution depending on the weight of piles