Part 4 - Preparing and installing domestic retrofit system 2 Flashcards
what is a warm flat roof?
A warm flat roof, or a built-up roof (BUR), is one where all the insulation (1) is above the joists/deck (2), making them part of the warm fabric of the building. The insulation is immediately below the waterproofing layer (3). The vapour control layer (4) is above the decking but below the insulation. The insulation can be adhered, mechanically fixed or loose laid.
what is a cold roof insulation?
A cold flat roof is one where the insulation (1) is between, or between and below, the roof joists (2). This is used more for retrofit, e.g., when refurbishing an existing timber joisted flat roof which has no insulation. The insulation is below the deck (3) but above the plasterboard (4). It allows insulation to be added without having to replace the waterproofing (5) on the existing roof or raising the roof line. It’s important to make sure that there is at least a 50mm air gap (6) for ventilation above the insulation and the roof deck to prevent condensation occurring.
what insulation is needed for IWI?
Rigid board‑PUR, PIR or PF
bullet
Mineral wool batts or wools
bullet
Wood fibre boards.
How do you install the PIR boards?
1Image 1 – foam adhesive applied to PIR board to finish off the wall. Smaller pieces should be fitted at the top.
Image 2 – deep fill any remaining gaps between the PIR boards and the wall/floor/ceiling with low expansion foam.
Image 3 – at window and door reveals, pieces of PIR board can be cut so they overlap the insulation on the main wall.
Image 4 – fix wall plug insulation anchors to each board and then cover with aluminium tape over the top of the anchor.
Image 5 – shaping and fitting the PIR to a sloping ceiling.
Plaster boArds finish
what is the fixing method for custom build EWI projects
Use of both adhesive (image 1) and mechanical fixings (image 2)
what do insulation boards need to be protected from?
bad weather
When drilling hole for cavity wall what should you do?
When drilling holes through the outer leaf, make sure they do not slope inwards towards the cavity
All drilling must be completed on one elevation and at least 2m of the adjacent elevations before injection commences on that elevation
bullet
Care should be taken when drilling next to building features. It’s advisable to drill at least two courses below such features.
Cavity wall insulation - drilling holes
Generally, a cavity wall Insulation system uses 22/25mm diameter holes. The distance between successive injection holes should be a maximum of 1.35m. Where possible, a diamond pattern should be used so that an injection hole in one row is midway between two holes in the rows above and below.
At the tops of walls and under gables, the topmost injection holes should not be more than 350mm below the upper edge of the cavity to be filled. Additionally, under horizontal boundaries, for example under eaves, windows or lintels, the centres between the topmost injection holes should not exceed 1.0m.
whats the machinery for cavity wall insulation and who does it have to be approved by ?
The machinery (image left) is specialist equipment and you need to be trained and competent in its use. Here are a couple of pointers.
Each blowing machine is identified as being approved by a plate/label showing the BBA certificate number.
how are wool density checked for cavity wall insulation
Density checks are carried out to make sure the machine is delivering the correct weight/volume
This is done by filling a test box and checking its weight, see the image below.
How should filling be proceeded for cavity walls?
Filling should proceed from the bottom to the top of walls and from the most to the least restricted sections. Filling from the bottom ensures a uniform fill.
The blowing machine is relatively simple to operate, 1 to 2 bales of wool can be emptied into the hopper at once
bullet
The hopper should always be kept half full
bullet
The feed rate is automatically controlled by a worm screw, and the only necessary adjustments will be to the:
Restrictor plate
Dump valve
Engine revs
what do you need to do in order to obtain the correct density fill for injected cavity insulation
insulation should be introduced into each injection hole in turn. Starting at one end of the elevation, and at the bottom of the wall, and working across from side to side
You will get a signal from the pressure switch that de-energises the clutches highlighting hole is full.
How do you make good the hole for injected cavity insulation
mortar mix should be made up before the installation begins. That way the preceding holes can be made good while the next hole is filling. It also allows adjustments to be made to the colour match when required.
How do you prepare for underfloor insulation?
- sort out the gaps between the floor and the gaps between the floor and the wall
2.the cables need to be sorted out
3.central heating pipework sealed with silicon