Part 2 Flashcards
Tuckman Model
- Forming - leaders direct
- Storming - decisions hardly made
- Norming - agreement
- Performing - strategically aware of what they are doing
- Adjourning - the end
RACI
responsibility
accountable
consulted
informed
effort driven scheduling
adding or removing resources to shorten the duration of the task.
does not however shorten total amount of work for that task
Net Present Value
discounting future cash flows back into today’s dollar comparison
contracts
an agreement between two parties
seller is obligated to sell the service
the buyer is obligated to pay for the service
Who assumes more risk vendor or customer
vendor assumes more risk for fixed contracts
customer assumes more risk for time and materials
techniques to shorten schedule
adjust resource summaries shorten lag time split tasks into smaller ones fast-tracking crashing reducing the scope
Earned Value Managment
integrates scope, time, and cost
requires have the baseline and the actuals for comparison.