P2 - Themes 2 Flashcards

1
Q

What are the different Plan levels / types?

A

Project

Stage

Team / Work Package (optional)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When are plans produced?

A

*Initiation Stage Plan (Starting up a Project)

*Project Plan (Initiating a Project)

*Stage Plans (Managing a Stage Boundary)

*Team Plans (with stage plan)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The Project Plan addresses what?

A

Time

Costs

Scope

Quality

Control Points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The Project Plan Identifies what?

A

Products

Activities

Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

7 Step Planning Approach

A

Design the plan

Define the product

Define activities / dependancies

Prepare time estimates

Prepare schedule

Analyse risks

Document the plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Name the Baseline Products

A

Business Case

Records / Registers

Reports

NB! Products aren’t just the finished goods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Product Based Planning Steps

A

Project Product Description (Scope)

Product Breakdown Structure (PBS)

Individual Product Descriptions (Project/Team Manager)

Product Flow Diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly