Memo 5100
Dictates communications procedure for SCL Trans
RTU Alarm comes in…
Look up RTU Details or ICCP links.
If missing one RTU signals > 30 min => call Comms group.
What is an ICCP?
Inter-control Center Comm Protocol = comm links to other utilities. Tested monthly. ICCP fail over.
First thing you do if an intertie with another utility trips?
Call the other utility, gather any available information.
If a tree causes a cycle, what is needed to fill out?
Tree Report, ROW Crew will notify you of level.
Diablo trash rack alarm comes in, what do you do?
Call Skagit Duty Sup
If you are placing a unit online per the schedule, make sure to do what?
Place in market mode.
What are the levels of SEL RELAY interrogation?
Level 1 - Read Only
Level 2 - Edit/Write
NWPP is only assured if requested within?
4 Minutes
When performing NSC Generator Test, what must be done?
Ensure Frequency is selected to anything but TFS 5 or 6 (Frequency button on BAL tab)
Dynamic Schedule:
A telemetered reading updated in real time and used as a schedule for AGC/ACE
Pseudo-Tie
A time varying energy transfer that is updated in real time and included in the actual net interchange (NIA)
List the steps that occur when a TPORS or NWPP reserve request comes through:
-BAAL automatically turns off
-On Unit Control
- Select a Ross Unit (Preferrably - or BN or DI)
- Take Control Mode to RAMP
- Take Regulation Mode to Reg/Assist
Enter load bias
Switching out underground cables?
Open opposite of bank side so that bank takes the discharge.