ON SITE GUIDE Flashcards
meter tails
- consumer tails - the cables between the electricity meter and the consumer unit & should be insulated & enclosed e.g in trunking or conduit.
- suppliers tails - the cables between the suppliers cut out and the electricity meter . should be protected fro mechanical damage.
where gas installation pipework is not separated from electricrical equipment , the following distances shall be followed :
- at least 150 mm away from supply equipment e.g consumer units
- at least 25mm away from electrical switches , sockets and cables.
Generators can be split into 2 classes
- Portable generators - with an electrical output rating of up to 10 KVA are used for short term use . e.g one day & are often isolated from earth. fault protection by electrical separation. basic protection by barriers or basic insulation of live parts
- Mobile generators - are those used for longer periods and can be excess of 10KVA output.
devices that offer protection against overload
- fuses , circuit breakers & RCBO
protection against electric shock :
automatic disconnection of the supply the most common form of protection against electric shock, there are 2 elements :
- basic protection - basic insulation around live part sand enclosure or barriers
- fault protection - protective earthing , bonding and automatic disconnection in case of a fault.
other methods of protection against electric shock
- SELV - supplied from isolated safety sources e.g a safety isolating transformer
- no live parts or exposed conductive parts are connected to earth or protective conductor & have reinforced insulation - PELV- pelv is same as selv except the circuits are not electrically seperated from earth.
automatic disconnection times for TN system
a. d.t of not more than 0.4 s required for final circuits not exceeding 63A with 1 or more socket outlets and 32A when supplying only fixed equipment.
- a.d.t of not more than 5 s for final circuits exceeding 32 A & distribution circuits
automatic disconnection times for TT system
- can only be achieved by protecting every circuit with an RCD , hence a time of not more than 0.2 s required for final circuits:
- not exceeding 63 A with one or more socket outlets
- 32 a when supplying only fixed equipment.
- a.d.t of not more than 1 s is permitted for:
final circuits not exceeding 63 A with one or more socket outlets and distribution circuits.
RCD,s
- a device that opeates when the residual current in the circuit reaches a certain value. they’re required for
- fault protection ( where earth fault loop impedance id too high to meet the disconnection time )
- addition protection for socket outlets not exceeding 32 a
- additional protection for lighting circutis in domestic.
- for cables without earthed metallic covering installed in walls
when are RCD’s not needed
- when a risk assessment determines rcd protection is not nessacary. risk assessment must be mentioned on certificate ( always needed in a dwelling )
- when cables are installed on the surface , rcd protection isn’t needed.
why are installations divided into circuits
- to minimize inconvenience and avoid hazards in the event of a fault .
where is SPD required ( protection against transient overvoltages ) which leads to :
- serious injury to or loss of human life
- interruption to an installation with a lots of people . e.g offices or universities.
types of Surge protection devices
- spds should have a protection level lower than the voltage and spds should be of the same make/ manufacturer
- type 1 - used only where there is risk of direct lightning current and typically installed at origin of the installation.
type 2 - used at distribution boards
type 3 - used near terminal equipment
aswell as combined type spds.
Arc Fault Detection Devices
- shall be installed at the origin of the circuit to be protected.
used for additional protection against fire in AC final circuits. designed to detect low level hazardous arcing that CB’s , Fuses and RCDs are not designed to detect
what is the purpose of protective earthing
to ensure that in the event of a fault , sufficient current flows to operate the protective device.
- e.g fuse to blow , rcd to operate and CB to operate in the required time. every exposed conductive part should be connected to the M.E.T
earth electrodes
- can be connected to the M.E.T by the earthing conductor and provides part of the earth fault installation for a TT system. ( shouldn’t exceed 200ohms)
types of earth electrode - earth rods - earth plates
ISOLATION & SWITCHING
means of isolation should be provided
- at the origin of an installation e.g a linked main switch or a CB should be used as a means to interrupt the supply on load
- for every circuit and every item of equipment ( have its own isolating device )
each device for switching off for mechanical maintenance must :
- be capable of switching the full load current
- clearly in OFF position
- be designed to avoid unintentional switching own
- be labelled.
each device for switching off for mechanical maintenance must :
- be capable of switching off the full load current
- clearly in OFF position
- be designed to avoid unintentional switching own
- be labelled.
Functional Switching
a switch must be installed in each part of the circuit which may require to be contorolled independently from other parts of the circuit
- switches shouldn’t be on the N conductor alone