Occupational Skills Flashcards
The purpose of a test pit or test hole is to?
Determine the soil conditions
The ground water table is the?
Average height below which the ground is saturated
Offset lines, in site layout, are used to?
Re-establish original building lines
Batter boards are used to?
Hold the building lines
An enlargement of a foundation wall to form a half column is called a?
A pilaster
The timber or steel beam used to carry the load while underpinning is called a?
A Needle
Where is a properly placed drain tile located?
Around the outside lower edge of the footing
What is the cross sectional area of a15M reinforcing bar
177mm2
A special type of enlarged view showing construction features more clearly is called a?
Detail drawing
Continuous lines extending to points off the same elevation across the surface of a plot of ground are called?
Contour lines
The measurements showing the location of the doors and windows are found on the?
Floor plan
On foundation plans, the footing is generally shown by?
Dashed lines
The order in which dimensional material should be given is
Thickness, width, length
Ex (2x4x10)
Ten foot 2x4
The minimum height of guard rails above platform level is
1067mm
42”
What is the purpose of a keyway in a footing
Eliminate shearing between the footing and wall
Stepped foundation footing walls are used for?
To help facilitate wall construction
A lally column is made up of?
Steel pipe and concrete
A projection on the outside of a foundation wall giving added support is?
Buttress
In precast concrete units, post tensioning is done when
After the concrete has cured
The main function of tie rods
To hold the forms a fixed distance apart
The horizontal form member used to align and strengthen panels is
Waler
What is the minimum cover for reinforcing steel for a wall exposed to the ground or weather
30mm
What is the main factor that determines the hydraulic pressure developed at the base of a wall
The height of the pour
Based on a definite water-cement ratio, a trial mix of concrete is found to have a 150mm slump.
How is this adjusted to a 75mm slump?
Use more sand and gravel
The advantage of a flexible anchor bolt is?
It allows space for adjustment
What will the result be of prestressing of precast concrete?
High tensile strength
The reinforcing steel in an open concrete stair and landing should be placed where?
Near the lower surface
A recess or opening at the top of a foundation wall is called?
A beam pocket
Why do tilt-up walls often require special reinforcing?
Because the concrete is subject to unusual strain due to the tilting
Why are mudsills required under the slab soffit jacks
To avoid point loading at the base of the Jack
Concrete:
What does the slump test measure?
Consistency of the concrete
Should the spacing of column yoked be closer at the bottom or at the top?
Closer at the bottom than at the top
Increasing the water cement ratio of a concrete mix will?
Decrease its strength
Metal pans in form work are used for?
Floors
The main purpose of concrete around a steel beam is to make it?
Fireproof
In concrete/masonry construction a groove into which metal flashing is fitted is called?
Reglet
The rough frame set into a masonry wall to which the finished frame is attached is called a
Buck
When two or more types of structural materials are used for load sharing it is referred to as
A composite column
A wooden column should not rest on a concrete floor because
Moisture may be drawn up from the slab causing the column to rot
The minimum end bearing for floor joists is?
38mm (1”1/2)
CODE
9.23.9.1
Except when supported on ribbon boards, floor joists shall not have less than 38mm length of end bearing
What is the purpose of placing the crown up when laying floor joists?
To compensate for deflection
A beam or floor joist which supports a header is called?
A trimmer
When framing openings in floors for stairs the joists should be?
Doubled around all openings
What is the purpose of cross bridging
To distribute the weight from one joist to another
To obtain the length of cross bridging with a framing square, what must first be known?
Spacing and height of the joists
What is the primary purpose of a box sill
To distribute transmitted wall load
The main purpose of mortar under the mudsill is to
Ensure uniform bearing on the concrete
Which of the following can be used to layout semi-circular arches
a) transit
B) trammel points
C) try square
D) architects scale
B) trammel points
When set into a brick wall the end of a joist or beam should be?
Cut on an angle toward the top edge
Why?
If there is a fire and the beam fails the cut helps prevent it taking the wall with it when it goes down
The angle of diagonal subflooring may be laid out with a framing square by using
Any two like numbers
What is the best method of determining the straightness of the wall plates
A string line and three blocks
The correct length of wall studding for a 2438 clear ceiling height on platform frame using 19mm finish flooring, lath and plaster ceiling and 38mm plates is?
Need to know that lath and plaster ceiling will be about 20-24mm
And that you would use 3 plates
2438mm - (38mm x3)
+ 19mm + 20mm
= 2362mm
Where would you find a lintel
Above a door or window opening
How is the size of a lintel determined
Width of the opening and the vertical load
A term for a board which is recessed in and nailed to studding for carrying floor joists is
A ribbon
A short vertical stud used above and below an opening is called?
A cripple
In the construction of a window opening, Jack studs are placed where?
Vertically at each side
Blocks set between the studs to prevent movement of air currents are called?
Fire stops
When sheathing up exterior walls on the floor, the walls are squared up by using?
Diagonal measurements
The framing member of a wall which fastens to the floor is called a
Sole plate
When the total rise for a common rafter is being checked, the measuring or line length of the rafter is found?
At the top outside edge from working point 1 to 2
If the hip Jack rafters are laid out 600mm o/c from the outside corner, the length of the third Jack on a 200 & 250 slope hip roof would be?
Use pythagoreum for the slope (200&250). Equals 320.156
Divide that by the run of the slope (250) to get the multiplier equals 1.28
Then: 600mm x 3= 1800
1800 x (multiplier 1.28)
=2304mm
The top end cut on a shortened bakey rafter is a
Square cut
The figures used on a square to layout the plum cut on an octagonal hip fit a 150 & 259 slope octagonal roof are?
150 & 271 m/o 150
The seat cut on a rafter for a gable roof with a slope 175 and 250 is laid out using
175 and 250 cut on 250
The common rafter line length for a roof that has a run of 4877mm and a rise of 3251mm is?
It is the hypotenuse of the rise and the run
Square root of:
4877 squared + 3251 squared
Equals: 5861mm
The length of a hip rafter for a 175 and 250 slope roof with 9000mm span is?
Find the multiplier for a 175 &250 slope
Trick:
hip value slope is 175 & 353.55
Multiplier is 1.116
ncommon and common are both 4500
A hip rafter is the square root of NCommon squared plus common squared x multiplier
A roof framing member between the hip rafter and the valley rafter is called
A cripple Jack rafter
The common difference in the length of the hip Jack rafters spaced at 600mm o/c with a 200 & 250 slope roof is
Find the multiplier
Sq/rt of 200sq +250sq
Then that answer divided by the run (250)
Multiple 600 by the multiplier
Equals 768
The unit length of a hip rafter in relationship to the valley rafter is?
Equal to the valley rafter
How many sloped surfaces does a mansard roof have
8
What could be done in order to bring cornices of an unequal pitch intersecting roof into alignment
Raise the plates of the minor span
The theoretical length of a ridge board for an equal pitch hip roof on a building 7315 wide by 13106 long would be?
13106 minus one full span 7315
(or two runs which still equal one span)
(7315/2) x2
Equals 5791
The theoretical length of a valley cripple Jack for a 200 and 250 slope roof placed 350mm from the intersection of the supporting and shortened valley is
Find the multiplier of a 200 & 250 slope
Equals 1.28
Multiply the multiplier by 350mm
Equals 448.21
Multiply that by two to get the valley length
Equals 869.437mm
The valley cripple Jack extends from?
Ridge to valley rafter