Objective 1 - PreConstruction Activities Flashcards

1
Q

What is required of bidders?

A

-Cost
-Insurance
-Bond - surety
-forms to be complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What consist of the bidding documents?

A

-Invitation to bid
- Instruction to bidders
-Information available to bidders
-Bid forms and attachments
-Bid Security
- Contract Forms: agreement, performance bond, payment bond, certificate
- Contract Conditions: general conditions, supplemental conditions
- Specification: Division through 49
Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the typical procedure for distributing documents and pre-bid meeting?

A

Must be sent out to to an advertising agency where public bidders and instructions can be viewed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Prequalification bidders procedures, when is it typically used

A

Bidders must demonstrate the following:
- Financial stability
- Bond security - showing they can financially protect themselves
- Size of firm
- Special training and staffing
- experience of project type
-Known history of dispute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the typical distribution of documents?

A

-Fair distribution to all bidders
- Includes written and graphic info, supplemental info, addenda, or additional instructions must be communicated simultaneously
- cost of printing sets of bid documents must be paid directly to the client
- electronic bids: - savings on printing and architect’s fees

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In distributing information control plan is established by client and architect, what is the process?

A

-Be consistent with disclosure of privacy policy
-clearly define documents distribution process
- provide supplemental info to all bidders in a timely and fair manner
-maintain secure exchange of project info

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the AIA documents applicable to bidding?

A

A710 - Instructions to bidders
A310 - Bid Bond Form
A101 - Owner-Contractor agreement
A503 - Supplementary conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A310 -Bid Bond Form

A

Guarantees that if the lowest bidders is to withdraw after selection but before execution of contract, the contractor is to pay the difference between the next lowest bidder and their bid.
-Bidders present: cost, schedule, unit prices, etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A710 - Instruction to Bidders

A

Notes the due date, time and location of pre-bid conference, last date bidders can call for questions, process of submitting questions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is architect’s role with Design-Bid-Build project delivery method during bidding?

A

-Help with reviewing bids
-seeing the qualifications for the bidders
-architect is initially engaged by the owner for design and documentations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the reasons to have multiple prime contractors?

A

a form of DBB that allows competitive biding, some public project require MP, accelerate schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly