Q

What are AIA contracts that define architect’s responsibilities during construction sit visits?

A
  • A201 - General Construction
  • G711 - Architect’s Field Report
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the architect’s responsibilities when it comes to applications to for payments to the contractor?

A

-Contractor submits an itemized app for payment
- Payments made by materials delivered and stored on site (or off site approved by owner before hand)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Certificate of payment

A

-Certifies that to the best of the architect’s knowledge the contractor has completed the work according or progress according to the CDs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are ways the architect can withold payments

A

-Contractor’s work is nonconforming
- contractor can not pay their subcontractors
- work cannot be completed for the contract sum
- work cannot be completed due to contract time