NEC - New Engineering Contract Flashcards

1
Q

Name 3 facts of NEC

A
  • first published 1993
  • a suite of contracts designed to promote partnering and collaboration between contractor and Client
  • recommended in Latham Report 1994 (constructing the team)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Name 3 intentions of NECs

A
  • stimulate good management
  • be clear and simple - in plain English, no legal terminology
  • be useable in a wide variety of situations from minor to major projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

NEC 3 published in 2005 suite of contracts include: (12)

A
  • the engineering and construction contract
  • the engineering and construction subcontract
  • the engineering and construction short contract
  • the engineering and construction short subcontract
  • the professional services contract
  • the professional services short contract
  • term services contract
  • term services short contract
  • supply contract
  • supply short contract
  • framework contract
  • the adjudicator’s contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Clause 10.1 states:

A
  • ‘the employer, the contractor, the project manager and the supervisor shall act as stated in the contact and in a spirit of mutual trust and cooperation.’
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Name the core clauses (9)

A
  • general
  • the contractor’s main responsibilities
  • time / programme
  • testing and defects
  • payment
  • compensation events
  • title
  • risks and insurance
  • termination
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Name the main contract options (6)

A
  • priced contract with activity schedule (closest to fixed term lump sum price)
  • priced contract with bill of quantities (contractor paid for amount of work done)
  • target contract with activity schedule
  • target contract with Bill of quantities
  • cost reimbursable contract (favours contractor)
  • management contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Contract administration facts (4)

A
  • project manager carries out 90% of contract administration
  • supervisor ensures quality complies with works information
  • no QS or Architect identified
  • certificates eg. Completion, defects, payment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Communications - name 6 facts

A
  • all communications take effect when received
  • contractor and project manager to act within contract timescales - COMPENSATION EVENT if period runs over
  • a notification is a separate communication - for defects, each has to be notified separately.
    This potentially creates a huge amount of work
  • early warning by contractor for increase in total prices, delay in completion / key date and performance is key
  • PM to enter early warning matters on risk register
  • risk can be reduced through meetings with contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Programme - an accepted programme is key to this contract type set out in Clause 31.2

Name contractor and PM duties (1 each)

A
  • contractor submits programme to PM for acceptance

- PM has 2 weeks to accept or notify reason for non-acceptance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a defect and when is the defects date?

A
  • defect: anything which is not in line with works information
  • defects date: end of notification period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Defects certificate - time driven NOT work driven.

What are the contractors responsibilities? (2)

What are the Supervisor’s responsibilities? (2)

A
  • contractor: prior to completion contractor to correct notified defects if it would prevent others doing there work (cl. 11.2C2)
  • after completion: contractor to correct notified defects before the end of the defects correction period (cl.43.2) JCT CONTRACTS SHOULD INCLUDE THIS
  • supervisor: May notify defect any time before defects date
  • supervisor issues defects certificate at last correction period.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Payment- name 1 supervisor duty and 1 Project Manager duty

A
  • assess amount due at each assessment date and certify within 1 week of assessment date
  • first assessment date decided by PM then in accordance with contract until 4 weeks after issue of defects certificate and full completion of works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does payment include? (3)

Amount due

A
  • price of works done to date
  • plus other amounts to be paid to contractor
  • less amounts to be paid / retained from contractor eg. Delay damages

(Including any tax, VAT 20%)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly