JCT Main Contracts Flashcards
1
Q
Traditional - lump sum Standard Building Contract with Quantities (SBC/Q)
Name where this type is appropriate and can be used
A
- appropriate for larger works designed / detailed by employer or on behalf of employer
- where an Architect / Contract Administrator and QS are to administer the conditions
- can be used: for Contractor design of discrete parts of the works (Contractors Design Portion
- where works are to be carried out in section
- by private and Local Authority employers
2
Q
Standard Building Contract without Quantities (SBC/XQ)
Name where this type is appropriate and can be used
A
- same as SBC/Q except degree of project complexity is not enough to require bill of quantities
3
Q
Intermediate Building Contract (IC) - not suitable as D&B contract
Name where this type is appropriate and can be used
A
- appropriate for simple building works with basic trades (no specialist design)
- works designed by or on behalf of employer detailed contract provisions. Employer to provide Contractor with drawings and bill of quantities and spec / schedule of works
- as previous - more detailed than Minor Works, less detailed than SBC
- can be used by both private and Local Authority employers
4
Q
Minor Works (MW)
Name where this type is appropriate and can be used
Note: both IC and MW are available with Contractor’s Design - allow CDP for part of works
neither are suitable for D&B.
A
- appropriate for simple work-designed by or on behalf of employer
- where employer is to produce drawings / spec / work schedules to define quantity and quality of works
- Architect / Contract Administer to administer conditions
- can be used by both private and Local Authority employers