NEC and JCT Contract Flashcards

1
Q

NEC Pre Contract

A

Contract Approach: Pro active and flexible and encourages early contractor involvement

Tendering Process: Open book and target cost options are available

Risk Allocation: Emphasises early engagement and risk sharing

Contract Structure: Modular with core clauses and optional ones tailored to project needs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

JCT Pre Contract

A

Contract approach: Prescriptive and risk-averse

Tendering Process: More structured and less flexibility in pricing options

Risk Allocation: Placed more on the contractor

Contract Structure: Standardised contracts with variations depending on procurement type

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

NEC Post Contract

A

Project Management: Active management with regular communication and collaboration

Payment Mechanism: More flexible with Early Warnings and Compensation Events to assess cost/time impacts

Changes & Variations: Changes are managed through Compensation Events, which require agreement on time and cost impacts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

JCT Post Contract

A

Project Management: More reactive and administratively focused with formalised procedures

Payment Mechanism: Follows a structured payment schedule with Interim Valuations and Variation Orders

Changes & Variations: Variations follow a formal instruction process, often requiring negotiation on cost/time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a bill of quantities

A

A document that provides a list of the estimated costs of materials, labour and equipment for a construction project. Has the prices and quantities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly