NEC Flashcards

1
Q

Can you give some examples of secondary options you included within your NEC contract for WHBG?

A

X7 - Delay Damages of £25,000 per week
X8 - Undertakings to the client or others
X15 - The contractors design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are Z clauses?

A

Z clauses are amendments to the core clauses within the NEC, contract amendments essentially

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are dangers with Z clauses?

A

Dangers being that poorly drafted Z clauses could be problematic if they do not work well with the standard core clauses already within the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is ‘Scope’ in NEC4 ECC contracts

A

Refers to extent and boundaries of the works that is required to be performed under the contract. Defines specific activities and deliverables the contractor is responsible for. Clients requirements such as design, drawings and spec.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you make an NEC contract D&B?

A

Design responsibility is set out in the ‘scope’, therefore if a D&B arrangement is required, it should be specified within the scope that all works are to be designed by the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is site information in NEC4 contracts?

A

Site information describes the existing and present conditions of the site e.g. survey info, existing as built drawings etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

can you outline the valuation process for WBHG

A

Contractor was to issue their application for payment on or before Assessment Date

From the assessment date, the PM had 7 days to issue the payment certificate (due date). After that, the client would have to pay the contractor 14 days after the payment certificate date (21 days after assessment date)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Role of a supervisor in NEC?

A

basically a CoW, assesses quality, notifies contractor of any defects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can the supervisor and PM be the same person

A

Yes on smaller projects like WHBG and BHS this happened.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly