Monitoring Progress Flashcards
1
Q
What might you include within a progress report?
A
- Date of visit.
- Weather at time of visit.
- H&S comments (if any)
- Progress (work this week).
- Work due next week.
- Contractors request for information.
- Client requests for information.
- Recent security issues.
- Meeting actions (actions agreed for each party).
- Progress photos.
2
Q
How often are site meetings typically held during a construction project?
A
- Weekly or biweekly meetings are common.
- Frequency depends on the project’s complexity.
- Meetings may be held as needed.
- Critical stages may require more frequent meetings.
3
Q
What is the purpose of an agenda in a site meeting?
A
- Organize meeting topics and discussions.
- Set clear meeting objectives and goals.
- Ensure efficient time management.
- Facilitate focused and structured discussions.
- Provide a roadmap for meeting participants.
- Prioritize important agenda items.
- Enhance overall meeting productivity and outcomes.
4
Q
What are the main topics discussed during a site meeting?
A
- Health and safety
- Matters arising
- Programme/progress of works
- Contract Instructions
- Contract documents
- Statutory issues
- Client comments
- Any other business
- Information required
5
Q
What is the critical path?
A
The critical path is the longest sequence of dependent activities that determines the shortest possible time required to complete a project.