Monitoring Progress Flashcards

1
Q

What might you include within a progress report?

A
  • Date of visit.
  • Weather at time of visit.
  • H&S comments (if any)
  • Progress (work this week).
  • Work due next week.
  • Contractors request for information.
  • Client requests for information.
  • Recent security issues.
  • Meeting actions (actions agreed for each party).
  • Progress photos.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How often are site meetings typically held during a construction project?

A
  • Weekly or biweekly meetings are common.
  • Frequency depends on the project’s complexity.
  • Meetings may be held as needed.
  • Critical stages may require more frequent meetings.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the purpose of an agenda in a site meeting?

A
  • Organize meeting topics and discussions.
  • Set clear meeting objectives and goals.
  • Ensure efficient time management.
  • Facilitate focused and structured discussions.
  • Provide a roadmap for meeting participants.
  • Prioritize important agenda items.
  • Enhance overall meeting productivity and outcomes.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the main topics discussed during a site meeting?

A
  • Health and safety
  • Matters arising
  • Programme/progress of works
  • Contract Instructions
  • Contract documents
  • Statutory issues
  • Client comments
  • Any other business
  • Information required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the critical path?

A

The critical path is the longest sequence of dependent activities that determines the shortest possible time required to complete a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly