Module 9 - DSDM Practice - MoSCoW Prioritisation Flashcards

1
Q

What is MoSCoW?

A

It is a prioritisation technique for helping to understand and manage priorities. The letters stand for must have, should have, could have, wont have this time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the Must Have requirements for MoSCow?

A

Must have requirements provide the minimum usable subset or must of requirements which the project guarantees to deliver

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the Should Have requirements for MoSCoW?

A

Should have requirements are defined as important but not vital. It may be painful to leave them out, but the solution should still be viable without them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the Could Have requirements for MoSCoW?

A

Could have requirements are defined as wanted or desirable but less important. They have less impact if left out the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the Wont Have requirements for MoSCoW?

A

Wont have requirements are those considered and recorded in the priorities requirements list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the levels or prioritisation?

A
  • MoSCoW for the Project
  • MoSCow for the project Increment
  • MoSCow for the TimeBox
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

T or F
MoSCoW is a prioritisation technique for helping to understand and manage priorities?

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

T or F
The MoSCoW letters stand for: must have, should have, could have and wont have this time

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which of the following prioritisation rule defines requirements to provide the minim usable subset or must of requirements which the project guarantees to deliver?
1. Should Have
2. Could Have
3. Must Have
4. Won’t have this time

A
  1. Must Have
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following prioritisation rule defines requirements as important but not vital. it may be painful to leave them out, but the solution could still be viable without them.
1. Should Have
2. Could Have
3. Must Have
4. Won’t have this time

A
  1. Should Have
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which of the following prioritisation rule defines requirements as wanted or desirable but less important. They have less impact if left out of the project.
1. Should Have
2. Could Have
3. Must Have
4. Won’t have this time

A
  1. Could Have
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which of the following prioritisation rule defines requirements as those considered and recorded in the prioritised requirements list but agreed not be delivered by the project team
1. Should Have
2. Could Have
3. Must Have
4. Won’t have this time

A
  1. Wont have this time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which of the following is the correct arrangement of the levels of prioritisation?
1. Project increment >Timebox > for the project
2. For the project > Project increment > Timebox
3. For the Project > For the timebox > for the project increment
4. Project increment > for the project > Timebox

A
  1. For the project > Project increment > Timebox
How well did you know this?
1
Not at all
2
3
4
5
Perfectly