Module 4 & 5 Flashcards
Servant Leadership
Common in agile projects. It’s the practice of leading through service to the team, by focusing on understanding and addressing the need and development of team members in order to enable the highest possible team performance
Power/interest grid:
Groups stakeholders on the basis of their levels of authority and interest in the project.
Power/influence grid:
A classification model that groups stakeholders on the basis of their levels of authority and involvement in the project.
Salience model
A classification model that groups stakeholders on the basis of their level of authority, their immediate needs, and how appropriate their involvement is in terms of the project.
EVM (Earned Value Management)
A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.
Projected budget at completion (BAC)
Represents the original project budget.
Planned Value (PV)
The authorized budget assigned to scheduled work.
Cost Variance (CV)
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.
CV = EV - AC
Schedule Variance (SV)
Measure of schedule performance expressed as the difference between the earned value and the planned value.
SV = EV - PV
Cost Performance Index (CPI)
Measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
CPI = EV / AC
Schedule Performance Index (SPI)
Measure of schedule efficiency expressed as the ratio of earned value to planned value.
SPI = EV / PV
Estimate at Completion (EAC)
The current projected final cost of the project.
EAC = BAC/CPI
Estimate to Complete (ETC)
The amount of money needed to complete the project.
ETC = EAC-AC
To complete performance index (TCPI)
TCPI is the calculated Cost Performance Index that is achieved on the remaining work to meet the specified management goal, such as the BAC or the EAC.”
The To Complete Performance Index is the estimate of the future cost performance that you may need to complete the project within the approved budget. This budget may be your initial approved budget (BAC), or a newly calculated on (Estimate at Completion).
TCPI = (BAC-EV) / (BAC-AC)
Variance At Completion (VAC)
Variance between the Estimate At Competion and the Budget at Competion. This is the difference between what the project was originally expected (baselined) to cost, versus what it is currently estimated to cost.
VAC = BAC – EAC
Earned Value (EV)
The measure of work performed expressed in terms of the budget authorized for
that work.
EV = % work complete to date x BAC
Actual Cost (AC)
The realized cost incurred for the work performed on an activity during a specific time period.
Burnup Chart
A graph to show the progress and gains made by the project team over time.