Module 4 Flashcards
Salience Model
A classification model that groups stakeholders on the basis of their level of authority, their immediate needs, and how appropriate their involvement is in terms of the project.
Power/Interest Grid
Groups stakeholders on the basis of their levels of authority and interest in the project.
Power/Influence Grid
A classification model that groups stakeholders on the basis of their levels of authority and involvement in the project.
SMART Objectives
Used to define key performance indicators
S-Specific: goal is focused and targeted
M-Measurable: must be able to measure target
A-Achievable: goal/peek performance must be doable
R-Relevant: target needs to be related to success
T-Time Bound: goal is not open-ended
Tuckman’s Ladder
- Forming: team members are making initial judgments about skills and personal qualities
- Storming: team members start to assert themselves and control issues as they emerge
- Norming: team starts to work productively without worrying about personal acceptance issues
- Performing: team is working at optimal productivity
- Adjourning: team completes project and shifts to the next one
Earned Value Management (EVM)
A methodology that combines scope, schedule, and resource measurements to assess project performance and progress during project execution.
EMV= I ($) * P
Earned Value (EV)
Tracking cost and effort performance against a planned value.
EV=% Complete X BAC
Cycle Time
Measurement of work that has progressed all the way from plan to completed or delivered.
Velocity
Measurement of total output form an iteration to attempt to predict future iteration outputs.
Throughput Metrics
Measurement of the team’s work that has moved form one stage to another stage over a certain time.
Planned Value (PV)
The authorized budget assigned to scheduled work.
Actual Cost (AC)
The realized cost incurred for the work performed on an activity during a specific time period.
Schedule Variance (SV)
A measure of schedule performance expressed as the difference between the earned value and the planned value.
SV=EV - PV
Schedule Performance Index (SPI)
A measure of schedule efficiency expressed as the ratio of earned value to planned value.
SPI=EV/PV
Cost Variance (CV)
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual costs.
CV=EV - AC
Cost Performance Index (CPI)
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
CPI=EV/AC
Estimate at Completion (EAC)
The current projected final cost of the project.
EAC=BAC/CPI