Module 3 -Projects Risks and Professional Ethics Flashcards
Strategies that are typically used to deal
with risks or threats that may have negative
impacts on project objectives if they occur
include all of the following EXCEPT:
A.Interpret
B.Avoid
C.Transfer
D.Mitigate
find answer
Risk transference nearly always involves:
A. Policies, procedures and risk avoidance
techniques
B. Accepting a lower profit if some activities
overrun their budget
C. Eliminating risk through risk mitigation
plan
D. Payment of a risk premium to the party
taking on the risk
find answer
The Delphi technique has all of the following
characteristics EXCEPT:
A. It is a way to reach a consensus of experts on a
subject such as project risk
B. It is a technique in which project risk experts
participate anonymously
C. It helps reduce bias in the data and keeps any one
person from having undue influence on the
outcome
D. It is an innovative solution to conducting risk
management analysis on a project.
find answer
Which of the following is NOT a tool or technique for gaining expert opinion as it relates to risk? A. Brainstorming B. Delphi technique C.Monte Carlo analysis D.Expert interviews
find answer
Your company is starting a new building project and
has assigned you the role of project manager. During
the first few meetings with stakeholders you become
aware of several risks that are of concern to the
project sponsor. The topic of risk management has
not been addressed yet. What is the first thing you
should do to address the project risks?
A. Develop a risk management plan
B. Identify project risks
C. Plan responses to project risks
D. Determine how risks will be controlled.
find answer
The BEST definition of risk management is:
A. The process of identifying, analyzing,
and responding to risk.
B. The process of reducing risk to the
minimum level possible for the project.
C. The process of proactively ensuring that
all project risk is documented and
controlled.
D. Creation of the risk response plan.
find answer
During which stage of risk planning are risks prioritized based on probability and impact? A. Perform Qualitative Risk Analysis B. Identify Risks C. Plan Risk Responses D. Perform Quantitative Risk Analysis
find answer
Which of the following is MOST likely to
interfere with attaining a project’s schedule
objective?
A. Delays in obtaining required approvals
B. Substantial increases in the cost of
purchased materials
C. Contract disputes that generate claims
for increased payments
D. Slippage of the planned postimplementation review meeting.
find answer
A project manager is quantifying risk for his
project. Several of his experts are offsite,
but wish to be included. How can this be
done?
A. Use Monte Carlo analysis using the
Internet as a tool
B. Apply the Critical Path Method
C. Determine options for recommended
corrective action
D. Apply the Delphi Technique.
find answer
Monte Carlo analysis is used to: A. Get an indication of the risk involved in the project B. Estimate an activity’s length C.Simulate the order in which activities occur D.Prove to management that extra staff is needed
find answer
While preparing risk responses, you identify additional
risks. What should you do?
A. Add reserves to the project to accommodate the
new risks and notify management.
B. Document the risk items and calculate the
expected monetary value based on probability and
impact that result from the occurrences.
C. Determine the risk events and the associated cost
then add the cost to the project budget as a
reserve.
D. Add a 10 percent contingency to the project budge
and notify the customer.
find answer
. Pareto charts help the project Manager: A. Focus on the most critical issues to improve quality B. Focus on stimulating thinking C. Explore a desired future outcome D. Determine if a process is out of control
find answer
A Control Chart help the project Manager: A. Focus on the most critical issues to improve quality B. Focus on stimulating thinking C. Explore a desired future outcome D. Determine if a process is functioning within set limits
find answer
What is a Run Chart? A. Same as a Pareto Chart and shows the aggregation of defects B. A pie chart that shows the distribution of various defects during the execution phase C. A bar graph that shows the occurrence of defects during the execution phase D. A line graph that shows trends in process over time, variation over time or declines/improvements in a process over time.
find answer
As the project manager, you have created a bar graph of problems and their frequencies. What is this kind of chart called? A. Deming chart B. Pareto chart C. Ishikawa chart D. Run chart
find answer