MOC EXAM 25Q Agile 100% 226->250 Flashcards

1
Q

You are working through your project and performing quality inspections on the product. During inspection, you notice a key part of the product is likely to be defective in the future. The team brainstormed, removed some scope and managed to make the product work without the defective component. This is:

  • Risk mitigation
  • Transfer of risk
  • Risk avoidance
  • Work-around
A

Risk avoidance involves taking focussed action to reduce the negative effect of uncertainty on the project, e.g. the removal of high risk scope elements from the project.
Process Groups Practice Guide (2022), page 303.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A Work Performance Report is a document containing organized information about project performance in a report format to enable decision making & actions and project communications. Which of the following is a type of Work Performance Report?

  • Status reports
  • Status of deliverables
  • Forecasted estimates to complete
  • Implementation status for change requests
A

The different types of Work Performance Report from the PMBOK:
1. Status reports
2. Memos
3. Justifications
4. Information notes
5. Electronic dashboards
6. Recommendations
7. Updates