Agile - NOTES To Continue Flashcards

1
Q

Defects that make it through testing and into a release are called ….

A

Defects that make it through testing and into a release are called “escaped defects.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Fast failure means …

A

Fast failure means that particular feature or proof-of-concept effort was not successful.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The risk-adjusted backlog is a ……. or …….. backlog containing risk ……… tasks for actionable risks.

A

The risk-adjusted backlog is a sprint or release backlog containing risk response tasks for actionable risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The whole team approach ensures team members ARE ……

A

The whole team approach ensures team members ARE multi-skilled, and have at least one deep specialty. “T-SHAPE”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

By completing the high-risk items first …..

A

By completing the high-risk items first, you are significantly reducing those risks and the threat of unknowns later on in the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

An Agile team is made up of …….

A

An Agile team is made up of generalising specialists, or “T-shaped” people with one deep knowledge area and a wide range or experience in other areas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The Team Facilitator, also known as the ………

A

The Team Facilitator, also known as the Scrum Master, Team Coach, Iteration Manager, Project Manager, Servant Leader and many other names. Their role is to help raise and remove blockers for the team, ensure an active flow of work, and problem solve with the team when needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The Team Facilitator, role is to help ….. and ….. ……….. for the team, ensure an active flow of work, and problem solve with the team when needed.

A

The Team Facilitator, role is to help raise and remove blockers for the team, ensure an active flow of work, and problem solve with the team when needed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Problem solving is done with ……..

A

Problem solving is done with the Agile team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Blockers are raised as soon as possible – at least during a daily stand-up, so the team can ……………

A

Blockers are raised as soon as possible – at least during a daily stand-up, so the team can swarm around the problem, get help from any experts needed, and move on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

”Pair programming” is a common technique in Agile and can be used for most tasks. Pairing up team members on a task or iteration gives them ……..

A

”Pair programming” is a common technique in Agile and can be used for most tasks. Pairing up team members on a task or iteration gives them the opportunity to talk and work with each other one-on-one

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. The three C’s of User Story Creation include:
    ……………
A
  1. The three C’s of User Story Creation include:
    • Creating the card
    • Conversation with the Product owner and developers to explain how the software or design will be used, and
    • Confirming the acceptance criteria and the definition of done.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Lead time is a concept from Lean and the Toyota Production System. …….

A

Lead time is a concept from Lean and the Toyota Production System. Whenever you are calculating Cycle time (smaller items such as processes, story cards, or an iteration in a larger project) or Lead time (larger items such as features or the project itself) you must take into consideration both : value-added time (that directly contributes to the customer outcome) and non-value-added time (that does not directly contribute to the customer outcome).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The product owner should “share” ……..

A

The product owner should “share” the updated items in the product backlog with the team and ensure a shared understanding “before” moving forward.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Agile uses fast visual mock-ups or prototypes such as storyboards, wireframes, or models, to get ……..

A

Agile uses fast visual mock-ups or prototypes such as storyboards, wireframes, or models, to get a quick understanding of the requirements and consensus from all stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

the whole team approach aims to bring ……

A

he whole team approach aims to bring all necessary people into the project team, ideally in a co-located space. It involves cross-functional team members who specialise in one skill and are fluent enough in a wide range of other skills.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Agile promotes sustainable development, where the team is ……..

A

Agile promotes sustainable development, where the team is not overburdened and is able to work at a constant pace indefinitely. Be wary of often switching tasks or pushing for too much work during each iteration – this will burn out individuals and ultimately slow down your progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The team self-assessment is used to …….

A

The team self-assessment is used to gauge the team members performance together, with the results helping to identify what is working well and where improvements can be made. The team then meets to problem solve improvements and to celebrate what is working well.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A pre-mortem looks at reasons …..

A

A pre-mortem looks at reasons for failure before they happen, and is a great way to brainstorm risks for a card or feature. Typically, team members write their reasons down then discuss in a round-robin style, as some people may come up with the same idea.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Agile encourages self-organizing teams, formed by ……….

A

Agile encourages self-organizing teams, formed by the people who created the requirements and had the desired outcome in the first place. This gives a higher level of ownership and product expertise, that often cannot be bought.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

There are many ways to reduce “wasteful” steps in the process of an agile team. We can stop :
1.
2.
3.
4.
5.
6.
7. …… and more.**

A

There are many ways to reduce “wasteful” steps in the process of an agile team. We can stop :
1. the introduction of unnecessary features,
2. reduce work in progress,
3. reduce delays and hand-offs,
4. extra processes,
5. task switching,
6. waiting,
7. defects and more.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

A sprint “retrospective” is held with the Whole Team, after a …………. but before the ……………..
We use it to ………. and look for …………, and everyone has a …. .. for feedback and to implement …….. before the next sprint.

A

A sprint “retrospective” is held with the Whole Team, after a sprint review but before the sprint planning meeting. We use it to gather lessons learned and look for opportunities for improvement, and everyone has a voice for feedback and to implement improvements before the next sprint.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

An Agile team charter typically covers :
1- ……..
2- ………..
3- ………….
4- …………

A

An Agile team charter typically covers :
1- Why we are doing the project,
2- Who benefits and how,
3- What does done look like, and
4- how are we going to work together
The Agile Practice Guide (2017), Chapter Five, p49

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Agile and lean frameworks include …………….

A

Agile and lean frameworks include Scaled Agile Framework (SAFe), Large Scale Scrum (LeSS), Scrum of Scrums, Dynamic Systems Development Method, along with the more common Kanban, eXtreme programming and Scrum. The Agile Practice Guide (2017), p110

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

The Product Owner adjusts the ……….. of product backlog items.
The team is responsible for ……………….. the effort for their work items.
Each time the team ……………………………..

A

The Product Owner adjusts the priority of product backlog items. The team is responsible for elaborating on and then estimating the effort for their work items.
Each time the team refines their estimates with a higher level of detail.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

The main difference between Scrum and Kanban is that ………..

A

The main difference between Scrum and Kanban is that Kanban teams employ a pull system. This means when an item of work is completed, it triggers someone to “pull” the next item in the queue onto the board to work on. Kanban teams work off a Kanban board that displays each task, and have a limit to how much work in progress (WIP) can be in place.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Given, When, Then is the way …………. is used, particularly when ……………..

A

Given, When, Then is the way BDD is used, particularly when outlining user Story Cards for your iteration. It highlights “Given” a certain situation, “When” something happens, “Then” we want this to happen.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

“Iterative” methods have ……….. requirements, …………………………………….., but delivered …………………..

A

“Iterative” methods have dynamic requirements, repeated with feedback until they are correct, but delivered only once. The Agile Practice Guide (2017), p18, Table 3-1.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Incremental project management approach includes ………………. requirements, performed …………………………., with ………… ………… deliveries.

A

Incremental project management approach includes dynamic requirements, performed once for a given increment, with frequent smaller deliveries. The Agile Practice Guide (2017), p18, Table 3-1.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Sprint Reviews are for ;;;;;;;;;;;;;;;;;;; Sprint Retrospectives are for ;;;;;;;;;;;;;;;;;;;;;;; where we ask “What went well, what didn’t go well, what did I learn?”

A

Sprint Reviews are for product demonstrations Sprint Retrospectives are for lessons learned, where we ask “What went well, what didn’t go well, what did I learn?”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

An Agile project can accept ……………. even late in development.
But while the competing constraints of cost, quality and schedule are often fixed, in Agile the scope can vary.
This means some features may need to ……………, as others become ……………….. A maintainable ………………. is required too - project managers must not ……….. the project team to increase the ………. of the project work.

A

An Agile project can accept changes even late in development.
But while the competing constraints of cost, quality and schedule are often fixed, in Agile the scope can vary.
This means some features may need to drop off, as others become prioritised. A maintainable pace of work is required too - project managers must not overwork the project team to increase the pace of the project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

A core component of Agile is ……. Management and ………..
Part of this are the various parts of the project information ……. (often physical, but can be tech-driven). This includes things such as the team …….., …….. board, the product …….., the ……… chart, the …….. test results and issues, and results of ………

A

A core component of Agile is Visual Management and **transparency.
** Part of this are the various parts of the project information radiator (often physical, but can be tech-driven). This includes things such as the team velocity, Kanban board, the product backlog, the burndown chart, the latest test results and issues, and results of retrospectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Working with business partners or someone who represents the customer almost daily is a key part of Agile. The team hears what the business would like the results to be, and meeting face to-face gets faster answers than reading documents, e-mails, or even having conference calls.

A

Working with business partners or someone who represents the customer almost daily is a key part of Agile. The team hears what the business would like the results to be, and meeting face to-face gets faster answers than reading documents, e-mails, or even having conference calls.

34
Q

A Predictive or Waterfall project management lifecycle focuses on …… requirements, performed ….. for the project for a …… delivery.

A

A Predictive or Waterfall project management lifecycle focuses on fixed requirements, performed once for the project for a single delivery.

35
Q

Agile projects centre around delivering business value, and working closely with the customers and business representatives to ensure that the value is always correct. Business risk and the impact of not undertaking the project must also be considered.

A

Agile projects centre around delivering business value, and working closely with the customers and business representatives to ensure that the value is always correct. Business risk and the impact of not undertaking the project must also be considered.

36
Q
  1. Agile is a combination of Incremental delivery and Iterative development. That means :
    • ………..
    • ………..
    • ………..
A
  1. Agile is a combination of Incremental delivery and Iterative development. That means :
    • business value is continuously and iteratively improved and prioritised,
    • while also being delivered in increments that the customer can see, feel and touch.
    • The features should be complete, tested, and quality is everyone’s responsibility.
37
Q

While it is common for the developers, testers and business representative to agree on the story card criteria, it is not signed off by the project sponsor directly. The product owner, representing the business and/or the customer, refines the feature backlog of work so they always know that business value is being delivered.

A

While it is common for the developers, testers and business representative to agree on the story card criteria, it is not signed off by the project sponsor directly. The product owner, representing the business and/or the customer, refines the feature backlog of work so they always know that business value is being delivered.

38
Q

Continuous Integration merges code to a test environment using an automated process, including automated regression tests to ensure nothing is broken. This allows the team to find and fix defects in the code more quickly. Test Driven Development writes a test first (which fails at first), then the code to ensure the test passes.

A

Continuous Integration merges code to a test environment using an automated process, including automated regression tests to ensure nothing is broken. This allows the team to find and fix defects in the code more quickly. Test Driven Development writes a test first (which fails at first), then the code to ensure the test passes.

39
Q

Minimum Viable Products (MVP) are usable features in their own right that are delivered incrementally. This allows for business value to be gained more quickly, while gathering feedback on the use of these features.

A

Minimum Viable Products (MVP) are usable features in their own right that are delivered incrementally. This allows for business value to be gained more quickly, while gathering feedback on the use of these features.

40
Q

Visual Management is a Lean principle borrowed into Agile, where we make key pieces of information as accessible as possible. Often found in the team area and often physical, it means anyone can walk through the area and see what they need at a glance. Kanban is an example of a low-tech / high touch tool.

A

Visual Management is a Lean principle borrowed into Agile, where we make key pieces of information as accessible as possible. Often found in the team area and often physical, it means anyone can walk through the area and see what they need at a glance. Kanban is an example of a low-tech / high touch tool.

41
Q

……….. does not add ……. to the project, and is not a ……. of Agile.

A

Busy-work does not add value to the project, and is not a benefit of Agile.

42
Q

The key to Kanban is making progress ………….. Progress naturally improves team ………… (no one likes being stuck, and blockers are clear for people to see and assist with).

A

The key to Kanban is making progress visible. Progress naturally improves team engagement (no one likes being stuck, and blockers are clear for people to see and assist with).

43
Q

Continuous integration is designed to merge all changes made to the software and …….. them …………, discovering any defects or issues on a …………. basis.

A

Continuous integration is designed to merge all changes made to the software and test them automatically, discovering any defects or issues on a daily basis.

44
Q

When voting in an Agile team, members who vote with a thumb sideways have a …………. or ……………. with the decision and would like to …………………………………...

A

When voting in an Agile team, members who vote with a thumb sideways have a concern or conflict with the decision and would like to discuss it further.

45
Q

Continuous integration aims to merge code and have a working build once a day, then executes automated tests quickly to see if anything is broken. This frequent checking ensures …………. …………….. passes before a problem is identified.

A

Continuous integration aims to merge code and have a working build once a day, then executes automated tests quickly to see if anything is broken. This frequent checking ensures less time passes before a problem is identified.

46
Q

Acceptance tests and criteria are designed before the development of a deliverable, and during elaboration, often in :
- a “G….., W….., t….” scenario
or an “…….,” “I want,” “……..,” scenario.

A

Acceptance tests and criteria are designed before the development of a deliverable, and during elaboration, often in :
- a “Given, When, then” scenario
or an “As a,” “I want,” “So I can,” scenario.

47
Q

The Agile project management approach includes ………….. requirements, …………….. until correct, with frequent …………….. …………………….

A

The Agile project management approach includes dynamic requirements, repeated until correct, with frequent smaller deliveries. The Agile Practice Guide (2017), p18, Table 3-1.

48
Q

An Agile project manager charters both …………………………………….. ………………….

A project charter focuses on (05) …………………………..

A Team Charter focuses on ……………………………. And is created as a team

A

An Agile project manager charters both the project and the team.
A project charter focuses on the business case, project purpose, high level requirements, stakeholders and risks.
A Team Charter focuses on the agreements in how the team will operate, and is created as a team.

49
Q

The definition of “…………..” is an important part of the Team Charter, to ensure the team knows when a task is completed, when they can pull the next tasks, and so everyone agrees what ……………….. ………….. …….. This could involve a card being defined, elaborated, developed, tested, reviewed and then released. The project sponsor may be included in the team charter, but does not need to sign off on it – it is an agreement amongst the team.

A

The definition of “done” is an important part of the Team Charter, to ensure the team knows when a task is completed, when they can pull the next tasks, and so everyone agrees what success looks like. This could involve a card being defined, elaborated, developed, tested, reviewed and then released. The project sponsor may be included in the team charter, but does not need to sign off on it – it is an agreement amongst the team.

50
Q

Agile Feature Driven Development starts with ;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;;; ;;;;;;;;;;;;;;;;;;;;;;;;;;;; ;;;;;;;;;;;;;;;;;;;;;;;;;. Once a feature is complete, the process can begin again, complete with any learning from the previous feature.

A

Agile Feature Driven Development starts with an overall feature model, then plans, designs and builds by those features. Once a feature is complete, the process can begin again, complete with any learning from the previous feature.

51
Q

Giving …………. of …………………… to the team and stakeholders is one way to gain their ……………… If stakeholders are involved in decision-making, they will be more ……….. To any decision made and to the project.

A

Giving ownership of decisions to the team and stakeholders is one way to gain their buy-in. If stakeholders are involved in decision-making, they will be more committed to any decision made and to the project.

52
Q

Visible ………………. helps maintain team ………………., and is facilitated through the use of the information …………….. :
- Kanban board,
- Burndown chart,
- Product backlog.
being clearly visible to all.

A

Visible progress helps maintain team engagement, and is facilitated through the use of the information radiator :
- Kanban board,
- burndown chart,
- product backlog.
being clearly visible to all.

53
Q

Agile methods recommend a team of ….. or fewer, typically between …………………. This keeps the communication ………………. small and ensures information travels ………………. for the team to do their work.

A

Agile methods recommend a team of 12 or fewer, typically between 3 and 9. This keeps the communication channels small and ensures information travels quickly for the team to do their work.

54
Q

The NPV calculation takes the ……………….. into consideration already,

A

💡 The NPV calculation takes the number of years into consideration already,

55
Q

The Opportunity Cost is the value of “the project ………………………..”

A

The Opportunity Cost is the value of “the project not selected.”

56
Q

The …… ……….. is the stage gate or phase review.
At the review, the progress of the project is evaluated and a decision is made whether to ……………… or ……………. the project.

A

The kill point is the stage gate or phase review.
At the review, the progress of the project is evaluated and a decision is made whether to continue or cancel the project.

57
Q

A hybrid project lifecycle approach incorporates parts of ……. (waterfall), ………, ……… and …….. It allows the project manager to tailor the approach to suit the situation.

A

A hybrid project lifecycle approach incorporates parts of Predictive (waterfall), iterative, incremental and Agile. It allows the project manager to tailor the approach to suit the situation.

58
Q

Return on Investment:
ROI =
………… / ……………

A

Return on Investment:
ROI = NET Income / Total Investment =
($240,000 - $200,000) / $200,000 x 100 = 20%

59
Q

The Benefit to Cost ratio:
BCR = …………… / ……………

A …………. value is better

A

The Benefit to Cost ratio :
BCR =Benefit / Cost.

A higher value is better

60
Q

The project which has the ………… internal rate of return (IRR) is the best choice.

A

The project which has the highest internal rate of return (IRR) is the best choice.

61
Q

Crystal’s core values include …….., …….. And ……, - in the same way as Agile is based around iterations over processes and tools - and understanding the impact things have on way of work and getting things done.

A

Crystal’s core values include People, Interaction and Community - in the same way as Agile is based around iterations over processes and tools - and understanding the impact things have on way of work and getting things done.

62
Q

Crystal
……, ….., ……, …. are based on factors such as people involved (0 to 8, all the way up to 100 or more), money involved and the general comfort level of the project.

A

Crystal Clear, Yellow, Orange and Red are based on factors such as people involved (0 to 8, all the way up to 100 or more), money involved and the general comfort level of the project.

63
Q

………………. demonstrate the strongest resistance to change in an organization.

A

People demonstrate the strongest resistance to change in an organization.

64
Q

** …………… Selection Criteria** are created to rate seller proposals.

A

Source Selection criteria are created to rate seller proposals.

65
Q

………-…… are used to:
- micro-commit to each other,
- uncover blockers, and
- ensure work flows freely through the team.

While everyone (including an executive) is welcome to join the stand-ups, they are not specifically for reporting to an executive team.

A

Stand-ups are used to:
- micro-commit to each other,
- uncover blockers, and
- ensure work flows freely through the team.

While everyone (including an executive) is welcome to join the stand-ups, they are not specifically for reporting to an executive team.

66
Q

“……….. ……………”, which are never a consideration in the decision for a project to continue.

A

“Sunk Costs”, which are never a consideration in the decision for a project to continue.

67
Q

Agile projects have short iterations enabling the project team to receive early and continuous feedback on product quality throughout the development lifecycle. By getting frequent customer feedback as the project progresses, Agile teams can incorporate most new changes into the product and the development process.

A

Agile projects have short iterations enabling the project team to receive early and continuous feedback on product quality throughout the development lifecycle. By getting frequent customer feedback as the project progresses, Agile teams can incorporate most new changes into the product and the development process.

68
Q

The process of writing a test that initially fails, adding code until the test passes, then refactoring the code is part of …………………………… (TDD).

………-………..-…………….. is the same as fail, pass, and streamline the code.

A

The process of writing a test that initially fails, adding code until the test passes, then refactoring the code is part of Test Driven Development. (TDD).

Red-Green-Refactor is the same as fail, pass, and streamline the code.

69
Q

You have an obligation to comply with the law of …………………….. country

A

You have an obligation to comply with the law of your base country

70
Q

The project manager role is more of a …………………. or an expediter than a complete project manager in a weak matrix organization.

A

The project manager role is more of a coordinator or an expediter than a complete project manager in a weak matrix organization.

71
Q

The different types of Work Performance Data (07):
1. ……… of work physically completed
2. ………. and ……….. performance measures
3. Start and finish dates of schedule …………
4. Number of …………….
5. Number of ……………
6. Actual ………..
7. Actual …………

A

The different types of Work Performance Data:
1. Percent of work physically completed
2. Quality and technical performance measures
3. Start and finish dates of schedule activities
4. Number of change requests
5. Number of defects
6. Actual costs
7. Actual durations

72
Q

Although ………… factors are not under your control, or the control of the organization, they can have as much …………. on your ability to execute a project.

A

Although external factors are not under your control, or the control of the organization, they can have as much impact on your ability to execute a project.

73
Q

Agile “…………… ……….”, or feature demonstrations, occur at the ……. of an iteration or when enough cards or features have been ……………….. into a set that can be showcased.

A

Agile “sprint reviews”, or feature demonstrations, occur at the end of an iteration or when enough cards or features have been completed into a set that can be showcased.

74
Q

Risk …………………. involves taking focussed action to reduce the negative effect of uncertainty on the project, e.g. the ……………. of high risk scope elements from the project.

A

Risk avoidance involves taking focussed action to reduce the negative effect of uncertainty on the project, e.g. the removal of high risk scope elements from the project.

75
Q

You have been asked to prepare a document to gain the project sponsor’s sign off to access their function’s resources, that details the project goal and business case, high-level scope and requirements, high level dates and milestones, a high-level budget, and initial risk analysis. you are creating the : …………. ……………….

A

You have been asked to prepare a document to gain the project sponsor’s sign off to access their function’s resources, that details the project goal and business case, high-level scope and requirements, high level dates and milestones, a high-level budget, and initial risk analysis. you are creating the : PROJECT CHARTER

76
Q

You are working on an Agile project and have been asked to create a document that lists team principles, agreements, and guidelines about the acceptable behaviour by team members. You are working on : THE ……. ………

A

You are working on an Agile project and have been asked to create a document that lists team principles, agreements, and guidelines about the acceptable behaviour by team members. You are working on : THE TEAM CHARTER

77
Q

The different types of Work Performance Report from the PMBOK:
1. ……….. reports
2. ………….
3. ………….
4. ……………
5. Electronic ……………
6. …………………..
7. ……………….

A

The different types of Work Performance Report from the PMBOK:
1. Status reports
2. Memos
3. Justifications
4. Information notes
5. Electronic dashboards
6. Recommendations
7. Updates

78
Q

To close out the project, a ………………………………… about the contract completion must be provided to the seller or supplier.

A

To close out the project, a formal and written notice about the contract completion must be provided to the seller or supplier.

79
Q

…………… …………………… is an estimation technique that uses data from past projects for an activity that is very similar in nature for cost or duration.

A

Analogous Estimating is an estimation technique that uses data from past projects for an activity that is very similar in nature for cost or duration.

80
Q

The Risk Management Plan drives and supports other risk management processes, so it should be done as ………… as possible.

A

The Risk Management Plan drives and supports other risk management processes, so it should be done as early as possible.

81
Q

Agile story cards should have:
- ………………. ,
- ………………..,
- ……………..
- ………………….

A

Agile story cards should have:
- the requirement,
- its criticality,
- test details and
- clear acceptance criteria.