Mechanics' and Materialmen's Liens Flashcards
Who is a “mechanic?”
People who build, improve, or repair buildings or repair/alter personal property
* Also includes those who supply materials (sometimes referred to as a Materialmen’s Lien)
What must the contractor file in the clerk of the court’s office?
A memorandum of lien, along with a certification that they have mailed a copy of the memorandum to the affected owner within 90 days of the completion of the work or as “otherwise terminated”
What is must be included in the memorandum of lien?
- Names and addresses of the owner of the property and of the claimant
- Amount of verified claim (and when payment is due)
- Intent to claim a lien
- Description of the property
- Date from which interest is claimed
- Claimant’s license number
- Notice to Owner (memorandum must be mailed to owner of property)
What property is subject to a mechanics’ lien?
Can only file to secure payment for work performend on behalf of owners of real property
* Can’t file for work performed at the request of a lessee
* Not permitted on public buildings
What are the rights of subcontractors and suppliers?
May obtain an independent mechanic’s lien by filing a memorandum and giving notice to the owner of the amount and character of the claim
What is a subcontractor’s lien limited to?
The amount owed by the owner to the general contractor when they receive notice
How can a subcontractor make the owner personally liable up to the amount of the general contractor’s liability?
Give notice to the owner before the work is done and file an affidavit with exact amount due within 30 days
What is the right to set-off?
The owner’s right, whereby any claim that the owner has against the “mechanic” may be subtracted from the claim that the “mechanic” has against the owner
How is a mechanics’ lien enforced?
By a creditor’s suit in equity
* Must be brought within 6 months from the time the memorandum was recorded OR within 60 days of the time the work ended, whichever is later
* Owner and affected creditor may plead SOL and owner may defend on grounds of poor workmanship
What is the priority of a mechanics’ lien?
Commences from the time work on the project started and takes priority over all liens except a lien for the value of the land perfected before the project started
* Subcontractor has priority over general
* Persons performing labor for subcontractor have priority over him
* Lienors furnishing manual labor have priority over materialmen to the extent of labor performed 30 days preceding the date of the performance of the last laborer
What is the owner’s right where the building is not completed?
Owner may set off against the amount still owed to the general contractor under the contract the amount necessary to complete the project
What is a mecahnic’s lien in personal property?
A lien for “just and reasonable charges” for alterations or repairs to a piece of personal property
What is the scope of a repairer’s lien?
By statute, mechanic obtains possessory lien when she is not paid for making requested repairs to personal property (i.e., possession is public act)
For how much money may a lien against the lawful possessor be asserted?
For $1,000
Who is considered a lawful possessor?
Both the owner and the holder of a security interest–so the mechanic’s lien takes priority over the holder of the security interest