Math Sheet Flashcards

0
Q

EV = EARNED VALUE

A

EV = % COMPLETE X BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

AC = ACTUAL COST

A

AC = CV/(CPI-1) special formula

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PV = PLANNED VALUE

A

PV = SV/(SPI-1) special formula

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

BAC = BUDGET AT COMPLETION

A

BAC = Summation(PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

EVM

A

EARNED VALUE MANAGEMENT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV = COST VARIANCE

A

EV-AC (>0) = on budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV = SCHEDULE VARIANCE

A

EV-PV (>0) on schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPI = COST PERFORMANCE INDEX

A

CPI = EV/AC (>1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SPI = SCHEDULE PERFORMANCE INDEX

A

SPI = EV/PV (>1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC = ESTIMATE AT COMPLETION

A

EAC = AC / % COMPLETE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ETC = ESTIMATE TO COMPLETION

A

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VAC = VARIANCE AT COMPLETION

A

VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI = TO COMPLETE PERFORMANCE INDEX

A

TCPI = REMAINING WORK/REMAINING BUDGET
(BAC-EV)/(BAC-AC)
(BAC-EV)/(EAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

QUALITATIVE RISK SCORE

A

PROBABILITY * (l scope + l schedule + l cost + l quality)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

EMV = EXPECTED MONETARY VALUE

A

EMV = IMPACT X PROBABILITY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

COMMUNICATION CHANNELS

A

COMMUNICATION CHANNELS = N(N-1)/2

16
Q

NORMAL DISTRIBUTION
SIGMA
STANDARD DEVIATION

A

1 Sigma = 68.26%
2 Sigma = 97.46%
3 Sigma = 99.73%
6 Sigma = 99.999%

17
Q

PV = PRESENT VALUE

A

PV = FV/(1+r)n

18
Q

PERT - PROGRAM EVALUATION & REVIEW TECHNIQUE

A

PERT = (O+4M+P)/6

O = Optimistic
P = Pessimistic
M = Most Likely
19
Q

SD OF ACTIVITY (sigma)

A

SD OF ACTIVITY SIGMA = (P-O)/6

20
Q

VARIANCE OF ACTIVITY

A

(SD)2

21
Q

FLOAT

A
FLOAT = LS-ES = LF-EF
LS = Late Start
LF = Late Finish
ES = Early Start
EF = Early Finish