Math Sheet Flashcards
EV = EARNED VALUE
EV = % COMPLETE X BAC
AC = ACTUAL COST
AC = CV/(CPI-1) special formula
PV = PLANNED VALUE
PV = SV/(SPI-1) special formula
BAC = BUDGET AT COMPLETION
BAC = Summation(PV)
EVM
EARNED VALUE MANAGEMENT
CV = COST VARIANCE
EV-AC (>0) = on budget
SV = SCHEDULE VARIANCE
EV-PV (>0) on schedule
CPI = COST PERFORMANCE INDEX
CPI = EV/AC (>1)
SPI = SCHEDULE PERFORMANCE INDEX
SPI = EV/PV (>1)
EAC = ESTIMATE AT COMPLETION
EAC = AC / % COMPLETE
ETC = ESTIMATE TO COMPLETION
ETC = EAC - AC
VAC = VARIANCE AT COMPLETION
VAC = BAC - EAC
TCPI = TO COMPLETE PERFORMANCE INDEX
TCPI = REMAINING WORK/REMAINING BUDGET
(BAC-EV)/(BAC-AC)
(BAC-EV)/(EAC-AC)
QUALITATIVE RISK SCORE
PROBABILITY * (l scope + l schedule + l cost + l quality)
EMV = EXPECTED MONETARY VALUE
EMV = IMPACT X PROBABILITY