Materials variance Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

What is materials variance?

A

It is the difference between the standard cost of materials for actual level of production and the actual cost of materials used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Overall materials variance =

A

(standard quantity x standard price) - (actual quantity x

actual price)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is materials price sub-variance caused by?

A

It is caused by the actual price per unit of the materials used being different from the budgeted price per unit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Materials price sub-variance =

A

Actual quantity x (standard price per unit - actual price

per unit)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is materials usage sub-variance caused by?

A

It is caused by the standard quantity of materials for the actual level of production being different from the actual quantity of materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Materials usage sub-variance =

A

Standard price x (standard quantity - actual quantity)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly