Materials Requirement Plan Flashcards
APP
6-12 month plan for independent demand items
MRP Inputs
- Master Production Schedule
- Item Master File
- Product Structure File
MRP Outputs
- Planned order releases
AKA When to place order and how much are we ordering
Master Production Schedule
Schedule of finished products
Combination of orders and forecasts
Item Master File
database of info on every item
part # & lead time
Product Structure File
bill of material for every final product produced
i.e. product structure tree
parts, quantity of each part, assembly sequence
Item
name or number identifying an item
LLC
Low Level Code
-lowest level item is seen at
LT
Lead Time
-time between order placed and order released
PD
Past Due
-orders behind schedule
Gross Requirements
Demand for the item
Scheduled Receipts
Quantity on order
Projected on hand
Quantity predicted to be on hand at the end of the last period
Net Requirements
quantity to be provided
-listed when needed
Planned order receipts
net requirement adjusted for lot size