MasterFormat Divisions Flashcards
Division 00
Procurement and Contracting Requirements
req.s for bidding including: bid solicitation, instructions to bidders, information available to bidders, bid forms, the agreement (contract), bonds and certificates and general conditions of the contract, supplementary conditions, addenda, and modifications.
Division 01
General Requirements
req.s applying to the entire project or all individual technical sections including: summary of the work, how pricing and payment will be handled, alternates, value analysis, contract modifications procedures, unit prices, construction progress documentation, submittal procedures (samples, shop drawings, etc) quality control, temporary facilities at the job site, product substitution procedures, owner-furnished items, special execution requirements and final cleaning and protection of the work.
Division 02
Existing Conditions
including: site remediation, site decontamination, subsurface investigation, surveying, selective demolition, etc.
Division 03
Concrete
including: forms, reinforcement, cast in place, precast, cementitious decks and underlayment, grouts and concrete restoration and cleaning
Division 04
Masonry
including: brick, concrete block, stone, terra cotta, simulated masonry, glass block and masonry restoration and cleaning
Division 05
Metals
including: all types of structural steel and other structural metals, ornamental metals, metal fabrications (stairs, ornamental ironwork, handrails, gratings, stair treads and nosing) as well as expansion joint covers and metal restoration and cleaning.
Division 06
Wood, Plastics, and Composites
typical structural wood framing, rough carpentry, finish carpentry and architectural woodwork. also including structural plastics, plastic fabrications, wood and plastic restoration and cleaning and other specialty composites.
Division 07
Thermal and Moisture Protection
includes dampproofing and waterproofing, insulation, vapor retarders, air barriers, shingles, roof tiles, siding,membrane roofing, flashing, joint sealers, fire and smoke protection, and roofing specialties.
Division 08
Openings
including: metal doors and frames, wood doors and frames, specialty doors, storefronts, all types of windows, skylights, hardware, curtain walls and glazing.
Division 09
Finishes
including: plaster, gypsum wallboard (including ancillary metal framing), all types of floor and wall tile, terrazzo, all types of flooring materials, acoustical ceilings and other types of decorative ceilings, wall coverings, acoustical treatments, paints, and other coatings.
Division 10
Specialties
catch all including: visual display boards, toilet compartments, louvers, grilles, wall and corner guards, access flooring, pre-built fireplaces, flatpoles, signage, lockers, awnings, storages shelving, and toilet and bath accessories
Division 11
Equipment
including: vaults and security items, teller and security, church-related, library, theater and stage, musical, mercantile, checkroom, vending machines, AV, loading-dock, detention, athletic, mortuary, medical equipment, and equipment for labs, and offices.
Division 12
Furnishings
includes: furniture, art, window treatments, multiple seating and manufactured (as opposed to custom) casework.
Division 13
Special Construction
covers: air-supported structures, special rooms (clean rooms, saunas, planteariums, etc) seismic control, radiation protection, lightning protections, hot tubs and kennels
Division 14
Conveying Equipment
including: elevators, escalators, dumbwaiters, moving walks and lifts
Division 21
Fire Suppression
includes: detection and alarms and all types of fire-suppression systems as well as standpipes and hoses.
note: fire-related materials (doors etc) are in their respective divisions