Mandatory & Core Experience Flashcards
Talk me through the pallet gate issue?
- Pallet gate didn’t provide enough headroom
- Installed in incorrect position
- Arranged a meeting to understand timeframes of rectification during the defects period to correct this
What is the RICS Guidance Note on Appropriate Contract Selection?
- Different procurement routes
- Different contract publishing bodied
- Provided useful information, however is now apart of the RICS QS and Construction Standards
How can a contract be adapted to suit the chosen procurement route?
- Depending on the procurement route a specific contract is chosen
- Traditional in JCT would be Major Project, Intermediate and Standard form, whereas D&B would be the D&B contract.
How did the consultant appointment tracker work?
- Recorded the consultant
- What form of appointment
- Comments sent / received
- Reviewed by solicitor
- Engrossed and Executed
Why have an advanced payment bond over an off-site material bond?
- Wanted to secure the steel price at a certain cost
- Agreed with the funder and the solicitor as the preferred course
Why does a non-completion notice need to be submitted to get LAD’s?
- Required in the JCT contract as a prerequisite to claim LAD’s
What is included in a Due Diligence report?
- Statutory Approvals
- Site Abnormals
- Legal Status
- Design Risks
- Utilities
- Procurement & Programme
14 Blackburn Road Design Change Control Procedure
- During the design phase
- Major change, PEP Change Control
- Request information on programme from designers
- Request new fee proposals for the scheme change as different involvement and abortive works
- Presented to the client
What is a design responsibilities matrix?
- Breakdown of the different design aspects of the project
- Consultants, Client and Main Contractor are assigned a RACI code to the different aspects
- Aim to prevent scope gaps
How do you manage a graduate?
- Very democratic leadership style
- Encourage discussion and questions
- Allow autonomy to undertake tasks and ask for help / review before issuing
How did you manage the risk register?
- Live document so updated continually as design progressed
- Meetings had ‘Risks’ section
- Assigned risks to consultants with a management / elimination process
What were the Strawberry Fields lessons learnt?
- Programme help, how long design stages took and earlier input of the interior designer
- Additional services missed in RFP’s were included within scopes. Allowance for more swept-path analysis or multiple DLSL modelling of schemes getting budget more accurate
What is the RICS Guidance note on Tendering Strategies
- Says what tendering is and
how tendering processes are used to establish a
contract price. - Explains the different tendering strategies
What is a negotiated tender?
- A single stage tender with one contractor that returns a single price which is then negotiated.
- Speed benefit
- Contractor involvement
- Loses competitive price
How do you calculate float?
- Work out how long there is between the activity before it impact on that activities start date
What are the principles of risk allowance?
- The amount added to the base cost estimate for items that cannot be precisely predicted to arrive at the cost limit (approved budget)
What is JCT Minor Works for?
- Small, relatively straight-forward construction projects, typically less than £250k in value.
- Last no more than 12 months.
- Client is responsible for procuring the design, including drawings, a specification, or work schedules.
- Or the contractor is responsible for designing specific parts of the works (Minor Works Building Contract with contractor’s design).
Who administers a JCT Minor Works Contract?
- Client can get a Contract Administrator
- Architect
How is snagging administering the contract?
- Makes sure the works are in an appropriate condition to issue a completion certificate.
What is the Iceberg model?
A tool that allows you to see further into a problem than the surface level. Based on 4 principles
What are the 4 Principles of the Iceberg Model?
- Events (what happened)
- Patterns (what are the trends)
- Structures (what influences / connects the patterns)
- Mental models (what values shape the system)
What is in a Stakeholder Management Plan?
- Documents how involved / influential stakeholders are. - Outlines the stakeholder communication plan, including when you’ll reach out to each stakeholder, what platform you’ll use, and how much information you’ll deliver.
What’s the difference between a creditor and debtor?
Creditor - You owe someone
Debtor - Someone owes you
Can you provide some examples of the questions you asked?
- Examples of similar schemes
- Prefer novation or stay client side
- Usual site attendance and inspection commitment
- Initial ideas
- Programme and expected involvement with the architect
What would you do prior to visiting the site?
- Correct PPE
- Undertake a risk assessment
- Ensure I receive site induction
- Informed of specific hazards of that day
Core Principal of Public Sector Procurement
Encourage free and open competition and value for money.
4 Principals of Public Procurement
TEMP
- Equality of Treatment
- Transparency
- Mutual Recognition
- Proportionality
What are Framework Agreements?
A trusted provider that ensures the suppliers that deliver your works, services, and goods have proven experience in the public sector
What are the public procurement threshold levels?
- Supplies and Services less than £213,000 (inc VAT)
- Works below £5.3m are below the Find a Tender Service threshold with anything over seen as a high-value contract
What does the threshold levels mean?
Anything over the threshold levels are subject to the full suite of regulations which are more onerous
Public Procurement Funding key issues
- Funding can be stopped or halted at any time
- Transferring money between departments and accounts is rigid
Public Procurement Motivations key issues
- Main focus is on ensuring public money is being spent wisely and transparently
- Must consider economic, environmental, and societal benefits of procurement approach before beginning