Managing Projects - Week 3 / Project Schedule Management Flashcards

1
Q

Process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule

A

Plan Schedule Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

For general purpose scheduling, use….

A

Microsoft Office Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

For Construction Management Scheduling use….

A

Oracle’s Primavera P6 Professional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Process of identifying and documenting the specific actions to be performed to produce the project deliverable

A

Define Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CHRONOLOGICAL IMPLICATIONS of what needs to be delivered?

A

Time Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Process of identifying and documenting relationships among the project activities

A

Sequence Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Process of estimating the number of work periods needed to complete individual activities with the estimated resources

A

Estimated Activity Durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Commonly measured in days, but for a short project it could be expressed in hours, or for a long project perhaps weeks may be more appropriate

A

Estimated Activity Durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Used to mark key deliverables or project stages and are given a zero duration

A

Milestone Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

“Plan Schedule Management” is simply

A
  • Develop Schedule
  • Monitor and Control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Time Management includes 5 processes:

A
  • Plan schedule management
  • Define activities
  • Sequence activities
  • Estimate resource requirements
  • Develop and control
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Process of estimating the number of work periods needed to complete individual activities with the estimated resources?

A

Estimate Activity Durations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Length of time an activity is expected to take to complete is known as

A

Duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The process of analysing activity sequences, durations, resource requirements, and schedule constraints?

A

Develop Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Most common form of project schedule analysis?

A

Critical Path Method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Most common method of project schedule presentation?

A

Gantt chart

17
Q

Common examples of schedule optimisation?

A

  - Network compression
- Resource levelling

18
Q

Process of monitoring the status of the project to update the project schedule and manage changes to the schedule baseline?

A

Control Schedule

19
Q

The easiest and most well practiced method ofdocumenting the logical sequencing of activities?

A

Network Diagram

20
Q

Preferred scheduling approach?

A

Critical Path Method

21
Q

The purpose of the forward pass in CPM is?

A

Calculate the earliest start and earliest finish dates

22
Q

Two Types of Schedules?

A
  • Gantt Chart
  • Network Diagram
23
Q

The purpose of the backward pass in CPM is?

A

Calculate the latest start and latest finish date

24
Q

Defined as the amount of float (slack) that can be used up without affecting the earliest start of any other activity within the schedule?

A

Free Float (FF)

25
Q

The shared float for all activities along a particular network branch?

A

Total Float

26
Q

Translate the logic of the network diagram onto a calendar grid?

A

Bar Chart

27
Q

Process of ensuring valuable resources are not overloaded or conflicted?

A

Resources Levelling (Smoothing)

28
Q

Developed with experts to develop a quick estimate; more accurate estimates are gathered later?

A

Rough Order of Magnitude Estimate (ROM)

29
Q

indicate the periods during which a resource is unavailable?

A

Resource Calendar

30
Q

May entail overtime or weekend work, increasing resources allocated to the project, or even rethinking the logic of activity sequencing (including fast-tracking)?

A

Accelerated Completion

31
Q

This approach is sometimes called crashing the program, or duration compression?

A

Accelerated Completion

32
Q

Inefficiencies, supervision problems and extra working overheads (infrastructure) are introduced that will have an upward effect on activity cost and a reduction in quality, and hence are not always wise decisions?

A

Duration Compression

33
Q

Each activity a range of values is provided that represent both the best case (optimistic) and worse case (pessimistic) in addition to the most likely scenario  in this way the probability of the project/event being completed on time can be objectively calculated?

A

Program Evaluation and Review Technique (PERT)

34
Q

Can be used to calculate a budget via the addition of the cost of all resources in the schedule?

A

Resource Implications

35
Q

Common objective to minimise the amount of time to complete a project (i.e. finish faster)?

A

Minimising Project Time

36
Q

Drawbacks to finishing more quickly?

A
  • Project costs may risen
  • Quality of finished work may fall
  • The agreed scope of work may come under pressure
  • Additional risk may be added
  • Larger contingency may be needed
37
Q

Something that needs to be balanced in order for overallproject performance to be maximised

A

Time