Managing Construction 15 Flashcards

1
Q

A COMPETITIVE bid can have THREE DIFFERENT types of DELIVERY METHODS:

A
  1. General Contracts
  2. Construction Manager
  3. Design-Build
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

GENERAL CONTRACTOR DELIVERY METHOD:

A

The owner hires an architect who designs the project, and those drawings are used to solicit bids or negotiate a price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CONSTRUCTION MANAGER delivery method

A

There are two types:

  1. CM Agency
  2. CM at Risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

CM AGENCY delivery method:

A

A firm is hired to represent the owner, but holds no subcontracts and is not legally responsible for the final const or schedule of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CM AT RISK:

A

The contractor takes responsibility for managing the subs, as well as stipulating a final price and schedule for the owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

DESIGN-BUILD delivery method:

A

The owner has only one contract, which is both for the design and construction of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the risk of the Design-Build delivery method?

A

Risk is increased for the contractor because the entire team is now responsible for both design and construction.