A COMPETITIVE bid can have THREE DIFFERENT types of DELIVERY METHODS:
- General Contracts
- Construction Manager
- Design-Build
GENERAL CONTRACTOR DELIVERY METHOD:
The owner hires an architect who designs the project, and those drawings are used to solicit bids or negotiate a price.
CONSTRUCTION MANAGER delivery method
There are two types:
- CM Agency
- CM at Risk
CM AGENCY delivery method:
A firm is hired to represent the owner, but holds no subcontracts and is not legally responsible for the final const or schedule of the project.
CM AT RISK:
The contractor takes responsibility for managing the subs, as well as stipulating a final price and schedule for the owner.
DESIGN-BUILD delivery method:
The owner has only one contract, which is both for the design and construction of the project.
What is the risk of the Design-Build delivery method?
Risk is increased for the contractor because the entire team is now responsible for both design and construction.