Managing a Stage Boundary Flashcards

1
Q

There are four activities which are done routinely at the end of a stage. What are the first 3 (before the end stage)?

A

* Plan the next stage

* Update the Project Plan

* Update the Business case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is involved in planning the next stage (the first activity in managing a stage boundary)?

A

Planning the next stage involves first:

* Create Stage Plan, Product Descriptions

Then

* Update PID, CIR, Risk Register, Issue Register, Quality Register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is involved in updating the project plan (the second routine activity done in managing a stage boundary)?

A

Updating the project plan involves:

* updating the project plan

* issue register

* risk register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is involved in updating a business case (the third routine activity in managing a stage boundary)?

A

Updating a Business case involves:

* updating the business case

* benefits review plan

* risk register

* issue register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the fourth routine activity at the end of a stage - what does it involve and what does it trigger?

A

The fourth routine activity at the end of stage is “Report End Stage”.

It involves:

  • Create End Stage Report, Lessons Report, follow-on action recommendations

This triggers:

* Request to approve next Stage Plan

* Request to approve Exception Plan (if applicable)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the final activity involved in managing a stage boundary that only happens sometimes, and in what circumstances does this occur?

A

The final activity involved in managing a stage boundary is only used if the stage or project enteres exception and an Exception Plan is requested.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens in practice if a project enters exception and an exception plan is requested?

A

* A stage boundary is inserted and an Exception Plan is prepared

* After this the Project Plan and Business Case are updated

* The End Stage report is also produced for the new stage boundary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the objectives of the managing a stage boundary process?

Mnemonic (APRPRR) (All People Reach Prison Riding Recklessly)

A

A - Assure the Project Board that all produces in the current Stage Plan have been completed as defined

P - Prepare the Stage Plan for the next stage

R - Review and if necessary update the PID

P - Provide the information needed for the Project Board to assess the continuing viability of the project

R - Request authorisation to start the next stage

R - Record any information or lessons that can help later stages or project, and obtain authorisation for the start of the next stage, together with its delegated tolerance margins

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly