What is the scope of Capacity Requirement Planning?
check production plans real feasibility during all stages of the planning and execution
What is the definition of capacity ?
The capability of any resource in a company to produce some output per time period
how it is called capacity requirement planning when referring to long-term?
resource requirements planning
what does Resource Plannings adds to the Strategic Planning?
Value, by validating the need and timing of capacity requirements recommending how to invest/divest capital to sustain the strategy execution
what is the priority of RCCP?
analyzing the current capacity bottlenecks, in terms of machines, materials or skilled labor
what is the scope of CRP?
to determine work center total load under the preliminary material requirements plan conditions, so to validate and release a feasible material requirements plan to execution and PAC
What components of LT accounts as work center load?
Setup + Run components
which are the components of LT?
- Queue
- Setup
- Run
- Wait
- Transfer
What does Queue represents?
a backlog of work waiting to be processed at work center