M3-A: Manage suoply Flashcards

1
Q

What does it mean when in a components in a BOM does not have an assigned used quantity?

A

That it cannot estimated at priori the quantity that will be used and the expense will be accounted as overheads

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is overplanning?

A

intentionally plan for higher than MPS quantities to allow safety stocks to match with demand variability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the action bucket in MRP?

A

The current time period where actions on order releases must be taken upon MRP suggestions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what is the minimum MRP planning horizon?

A

The product cumulative lead time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is one of the biggest MRP assumption
about lead times?

A

full child components availability at the time of parent component order release, that means that MRP accounted lead times only equals the parent component processing lead time without delays

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What it the Projected available in MRP?

A

is the projected available inventory for the item at the end of the referenced time period. This a projected available of 100 at t=tmeans that 100units will be available for customer orders fulfillment at t= t+1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what are the MRP inputs?

A
  • MPS requirements
  • BOM
  • Item master file (Lead time, Batch size)
  • Inventory status logs file (on hand, on order allocations,..)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What triggers MRP Offsetting?

A

the presence of a Net Requirement as the result of projected available depletion due by gross customer order requirement for that period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly