M2 CONCEPTS Flashcards

1
Q
  • supports the weight of a structure and its applied loads
  • is a part of a building’ s substructure
A

Foundation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Major Types of Foundation Systems

A

1.Shallow Foundation
2.Deep Foundation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What type of foundation should be used in these conditions?

  • Strata of good bearing capacity is not available near the ground
  • Spread footings are not allowed due to restrictions in space
  • Design requirements due to possible space and layout constraints
A

Deep Foundation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  • simplest and most common type of building foundation
  • usually a square or rectangular reinforced concrete pad
  • distribute building loads over an area
A

Spread Footing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

support a wall and one or more columns, or several columns

A

Combined Footings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

consist of a heavily reinforced concrete slab extending under the entire structure, in order to spread the structure’ s load over a large area.

A

Mat or raft foundations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

a type of mat foundation in which the weight of the soil excavated approximately equals the weight of the structure being erected.

A

Floating Foundation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

nothing more than a column driven into the soil to support a structure by transferring building loads to a deeper and stronger layer of soil or rock.

A

Pile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Classification of Piles

A
  1. End Bearing Piles
  2. Friction Piles
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Types of Piles:

Manufactured in almost any desired size or shape. Commonly used section shapes include round, square, and octagonal shapes.

A

Precast Concrete Piles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Types of Piles:

constructed by driving a steel shell into the ground and then filling it with concrete.

A

Cast-in-place concrete piles (or shell piles)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Types of Piles:

capable of supporting heavy loads, can be driven to great depth without damage, and are easily cut and spliced.

A

Steel piles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Type of Piles:

piles made up of two or more different materials.

A

Composite Piles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Type of Piles:

also known as compacted concrete piles, Franki piles, and pressure injected footings. They are a special form of cast-in-place concrete pile in which an enlarged base (or bulb) is formed during
driving.

A

Bulb Piles

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Two Common Pile Construction Methods

A
  1. Pile Driving
  2. Bored Piles/ Cast-in-situ
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Deep Foundation Load Test:

This method evaluates pile bearing capacity by applying a dynamic load to the pile head and measuring acceleration and strain.

A

Dynamic Load Test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Deep Foundation Load Test:

  • Incremental static loads (5 or 10 tons) applied using a hydraulic jack.
  • Holding Time: Each load increment is held for 2.5 minutes.
  • Failure Criteria: Testing stops if the pile requires constant pumping to hold the load.
  • Settlement Readings: Recorded immediately after stopping and at 2.5-minute intervals for 5 minutes.
  • Load Removal & Recovery: All loads are removed, and recovery readings are taken at 2.5-minute intervals for
    5 minutes.
A

Static Load Test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A non-destructive test (NDT) used to detect defects like cracks and changes in cross-section.

A

Pile Integrity Test (PIT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A highly accurate pile integrity test for deep foundations, it uses ultrasonic pulses between probes to detect anomalies within concrete.

A

Cross-Hole Sonic Logging (CSL) Test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

simply a column, usually of reinforced concrete, constructed below the ground surface.

A

Pier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

a structure used to provide all-around lateral support to an excavation. It may be either open or pneumatic.

A

Caisson

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

the ease with which water flows through the soil, is primarily a function of a soil’s grain size distribution.

A

Soil Permeability

24
Q

one of the world’s most versatile and
widely used construction materials.

A

Concrete or Portland Cement Concrete

25
Order of concrete pouring
Columns are usually constructed prior to casting the girders, beams, and slabs to eliminate the effect of shrinkage of column concrete on the other members
26
concrete that has been cast into the desired shape prior to placement in its permanent position in a structure or building.
Precast Concrete
27
a special form of precast wall construction in which wall panels are cast horizontally at the job site and then erected.
Tilt-up Construction
28
a concrete element to which an initial compression load has been applied.
Pre-stressed Concrete
29
Two Methods for Pre-stressed Concrete
1. Pre-tensioning 2. Post-tensioning
30
Processes in Concrete Delivery
1. Batching 2. Mixing 3. Transporting 4. Placing 5. Consolidating 6. Finishing 7. Curing
31
Test performed to check the quality of a batch of concrete during construction.
Concrete Slump Test
32
Preferable time of Concrete Pouring
Night time | preferable to pour concrete at night, when the temperature is descending
33
# **TRUE or FALSE** Pour concrete directly into column forms from the hose. Do NOT let it flow through beams to the column.
FALSE | Do NOT pour concrete directly... Instead let it flow through beams...
34
# **TRUE or FALSE** For walls, avoid pouring concrete horizontally to prevent segregation. Focus on one location and allow the concrete to flow horizontally.
TRUE
35
# **TRUE or FALSE** The heap height should exceed 250 mm to avoid overloading slab forms and supports. Monitor the bar arrangement during pouring and make adjustments before covering completely with concrete.
FALSE | Should NOT exceed 250 mm
36
the process of removing air voids in concrete as it is placed.
Consolidation
37
The most effective method of consolidation, but it must be performed correctly to prevent defects.
Vibration
38
Types of Concrete Finishing
1. screeding 2. floating 3. troweling 4. brooming
39
# **Fill in the blank:** Concrete curing hydration requires **[BLANK]** with sufficient moisture
3 days to 40 - 80°F
40
# **TRUE or FALSE** The rate of hardening of concrete is greatly reduced when concrete temperature is appreciably higher than the optimum temperature of 50 to 60° F (10 to 15.5° C).
FALSE | rate of hardening is greatly ACCELERATED
41
# **TRUE or FALSE** High temperatures, especially when accompanied by winds and low humidity, greatly increase the shrinkage of concrete and often lead to surface cracking of the concrete.
TRUE
42
Forms shape and support freshly placed concrete, ensuring proper size, alignment, and stability during construction. a temporary structure that must bear all loads, including its own weight.
Formworks
43
Made on-site using timber, plywood, or particleboard. Though flexible and cost-effective where labor is cheap, it is time-consuming for large structures and has a short lifespan.
Conventional Formwork
44
Modular, designed for efficiency, accuracy, and waste reduction. Often include built-in safety features.
Modern Formwork Systems
45
Prefabricated metal-framed modules (steel/aluminum) with different surface coverings (steel, aluminum, timber, etc.). Benefits include faster construction and lower life-cycle costs.
Engineered/Pre-fabricated Formwork
46
# **TRUE or FALSE** Formwork installation must be rigid, precise, reusable, and NOT easy to strip
FALSE | should be easy to strip when concrete has cured
47
Formwork Classification by Materials
* Timber * Plywood * Steel * Aluminum * Plastic
48
# **Classification By Materials** Advantages * easy to cut into size and shape * light in weight * easy to handle * easy to replace the damaged parts * easy to dismantle Disadvantages * dry timber may absorb water * lengths are limited * few reuses * relatively cheap
Timber
49
# **Classification By Materials** Advantages * easy to cut into size and shape * smooth finish on the surface * possible curved form * large size sheets are available Disadvantages * thin sheets not for heavy concrete * more costly than timber
Plywood
50
# **Classification By Materials** Advantages * durable and strong * uniform and smooth surface finish * great reusability * easy to fix, and easy to dismantle Disadvantages * cost is comparatively higher (initially) * heavy in weight and requires lifting equipment * susceptible to corrosion
Steel
51
# **Classification By Materials** Advantages * easy to fix and dismantle * easy to handle * reusable several times * simultaneous casting Disadvantages * susceptible to deflection * higher comparative cost
Aluminum
52
# **Classification By Materials** Advantages * light and easy to handle * easy to make complex shape * resistant against water * recyclable damaged sheets * reusable, for good plastics Disadvantages * weak against heat * costly material * comparatively weaker in strength to steel
Plastic
53
Period of Removal for walls, columns, and vertical sides of beams of a building
1 to 2 days
54
Period of Removal for slabs (props left undr) of a building
3 days
55
Period of Removal for beam soffits of a building
7 days