How is AFAS affected by a loss of Y-10?
C-187A Channel is Lost
The channel goes to a tripped state. Logic = 1 out of 3 now.
Loss of power prevents the channel from being bypassed.
T.S. 3.3.3 Engineered Safety Features (ESF) Instrumentation
- Four ESF bistables and associated instrument channels for each Function in Table 3.3.3-1 shall be OPERABLE.
How is CIAS impacted by the loss of Y-10?
Left channel CIAS is lost.
If actual CHR/CHP perform EOP Supplement 6 and isolate left channel valves for CHP or CHR.
Containment Spray on CHP requires left channel spray initiation.
SIAS initiation on CHP requires push button.
T.S. 3.3.3/3.3.4
- 3.3 Engineered Safety Features (ESF) Instrumentation
* Four ESF bistables and associated instrument channels for each Function in Table 3.3.3-1 shall be OPERABLE. - 3.4 Engineered Safety Features (ESF) Logic and Manual Initiation
* Two ESF Manual Initiation and two ESF Actuation Logic channels and associated bypass removal channels shall be OPERABLE for each ESF Function specified in Table 3.3.4-1.
How is CRHVAC impacted by the loss of Y-10?
Left ‘A’ Train can’t be operated in Emergency.
If Left ‘A’ Train running, swaps to recirculation mode.
If running, VC-11 trips and won’t restart.
T.S. 3.7.10/3.7.11
3.7.10 Control Room Ventilation (CRV) Filtration
- Two CRV Filtration trains shall be OPERABLE.
- MODES 1, 2, 3, 4,
- During CORE ALTERATIONS,
- During movement of irradiated fuel assemblies,
- During movement of a fuel cask in or over the Spent Fuel Pool (SFP).
3.7.11 Control Room Ventilation (CRV) Cooling
- Two CRV Cooling trains shall be OPERABLE
- MODES 1, 2, 3, 4,
- During CORE ALTERATIONS,
- During movement of irradiated fuel assemblies,
- During movement of a fuel cask in or over the Spent Fuel Pool (SFP).
How does a loss of Y-10 impact the ADVs?
HIC-0780A, 0780B, 0781B Steam dump control at C-01 and C-33 no longer function.
Utilize TBV
T.S. 3.7.4 Atmospheric Dump Valves (ADVs)
One ADV per steam generator shall be OPERABLE.
MODES 1, 2, and 3,
MODE 4 when steam generator is being relied upon for heat removal
How is ‘A’ Pressurizer Level Control impacted by a loss of Y-10?
Fails to max charging and no letdown with ‘A’ channel PLCS in service.