An excavator has a bucket capacity of 2.8 yd3 … Assuming 8-hr workdays, the number of days required to complete the job is most nearly:
A. 9
B. 10
C. 11
D. 13
C. 11
An excavator has a bucket capacity of 3.0 yd3 … The number of trucks needed to balance the production of the excavator, assuming 8-hr workdays, is most nearly:
A. 2
B. 3
C. 4
D. 5
B. 3
The revised SOW is to substitute one layer of 5/8-in.-thick sheet rock
A. 3,300
B. 4,200
C. 9,800
D. 7,800
C. 9,800
A 450-ft-long canal (trapezoidal section: 19-ftbottom width, 3H:2V side slopes)
A. 75,000
B. 85,000
C. 95,000
D. 105,000
D. 105,000
Dump trucks with a capacity of 16 yd3 … The factors affecting the job site productivity of the dump truck are: 0.80 for equipment idle time and 0.70 for operator efficiency.
A. 3
B. 4
C. 5
D. 6
C. 5
A certain project includes the activities
summarized in the table below. The start date of the project is week 0. The project duration (weeks) is most nearly: (WITH TABLE)
A. 32
B. 36
C. 41
D. 44
C. 41
A 6-in.-square unreinforced-concrete beam is loaded in third-point loading on a simple span of 5 ft.
A. 6,500
B. 5,500
C. 4,500
D. 3,500
D. 3,500
A 6-in.-diameter × 12-in.-height concrete
cylinder fails at a transverse load of 55,000 lb. at 28 days in a split cylinder test.
A. 6,200
B. 5,200
C. 4,200
D. 3,200
B. 5,200
The blended cement mix contains
30% fly ash but no retarders.
A. 2,600
B. 2,760
C. 2,150
D. 2,300
A. 2,600
A temporary road closure
A. 4,800
B. 5,800
C. 6,800
D. 7,800
B. 5,800
Whenever a masonry wall is constructed, a limited access zone is to be established. Which of the following is true?
A. The limited access zone shall run to the same length on both sides of the wall.
B. The width of the limited access zone shall be wall height plus 2 ft.
C. The width of the limited access zone shall be wall height plus 4 ft.
D. If provided along the entire length of the wall, the width of the limited access zone is based on the judgment of the contractor.
C. The width of the limited access zone shall be wall height plus 4 ft.
lifelines shall be secured above the point of operation to an anchorage or structural member capable of supporting a dead weight (lb) of at least:
A. 5,000
B. 4,500
C. 4,000
D. 3,200
A. 5,000
the limiting exposure (dB) to impulse or impact peak noise level is most nearly:
A. 80
B. 100
C. 120
D. 140
D. 140
A job requires specially engineered fill to be hauled from storage to the job site and then placed and compacted.
A. 15
B. 27
C. 23
D. 22
D. 22
The following table shows areas of cut and fill sections at locations 50 ft apart. Assume shrinkage = 12% and bulking = 25%. Cumulative earthwork (yd3) between stations 0 + 0.00 and 3 +0.00 is most nearly:
A. 1,340
B. 1,850
C. 2,200
D. 2,500
A. 1,340
A contractor has the following options for a project lasting 18 months: … The benefit-cost ratio of option B (purchasing) is most nearly:
A. 0.95
B. 1.25
C. 1.55
D. 1.95
C. 1.55
An excavation plan is outlined in the following figure. Each grid square is 50 ft. × 50 ft. The numbers are depth of cut (ft.) at indicated locations. The total volume of cut (yd3) is most nearly:
A. 4,500
B. 5,000
C. 5,500
D. 6,000
A. 4,500
An existing landfill, in the shape of a truncated pyramid, is rectangular at the base with plan dimensions 4,000 ft. × 2,500 ft.
A. 525,000
B. 650,500
C. 712,200
D. 821,435
A. 525,000
The following table shows ordinates of a mass haul diagram for a highway construction project. The free haul distance is 300 ft. Overhaul cost is
$3.70/station-yd.
The total cost of overhaul is most nearly:
A. $35,000
B. $40,000
C. $45,000
D. $50,000
B. $40,000
… Labor cost for premium time is 50% for hours during the week, and 80% for weekend work. What is most nearly the overall labor premium rate for the project?
A. 1.25
B. 1.28
C. 1.31
D. 1.34
A. 1.25
A roller is used to compact soil to a specific density. The roller can achieve this target density for a 6-in. layer of material in four passes.
A. 1
B. 2
C. 3
D. 4
B. 2
A 14-ft-high wall is placed at a rate of 4 ft./hr. Concrete is lightweight (135 pcf) made with Type I cement and a retarding admixture.
A. 870
B. 750
C. 900
D. 725
A. 870
… . The maturity curve (Nurse-Saul) for the concrete is shown in the figure below.
A. 24
B. 36
C. 48
D. 60
C. 48
An activity on an arrow network for a project is shown below. Numbers adjacent to arrows are activity durations (weeks). The total float (weeks) for activity G is:
A. 0
B. 1
C. 2
D. 3
B. 1
As part of the PERT analysis of a project,
durations are estimated for activities A through G and summarized in the table below. The critical path for the project is ACEF … The probability (%) that the project will be completed in less than 25 weeks is most nearly:
A. 12
B. 18
C. 20
D. 22
D. 22
A new earth haul project requires moving 323,000 ft3 (bank measure) of excavated material to a location 12 mi away. A bidding contractor had completed a similar project (size and scope) 2½ years ago. The proposed price for the job on record was $525.00 per dump-truck load. Annual construction inflation factor is 3.2%. The
contractor uses a fleet of dump trucks with 26-yd3 capacity (heaped). The excavated material has a swell factor of 25%. The contractor’s bid ($) should
be most nearly:
A. 262,000
B. 302,000
C. 326,000
D. 353,000
C. 326,000
A building construction site is represented by the following rectangle ABCD. The original elevation of the water table at the site is 325.8 ft (above sea level). The dashed line shows the limits of proposed construction. (HOLLOW RECTANGLE)
A. 1,000
B. 1,500
C. 2,000
D. 3,000
D. 3,000
A contract has 90 days remaining until
completion. Early completion will be paid $18,000 bonus per day that the duration is shortened.
A. 1 additional crew unit
B. 2 additional crew units
C. 3 additional crew units
D. None of the crashing schemes are profitable
A. 1 additional crew unit
The activity on a node diagram for a project is shown below. All durations are in weeks. All relationships are finish to start unless noted otherwise. The free float (weeks) of activity A is:
A. 0
B. 1
C. 2
D. 3
A. 0
All costs for a construction project are
classified as either direct costs (material, labor, etc.) or indirect costs (leasing and rental costs,
utilities, etc.). The estimated variation of these cost categories vs. project duration (weeks) is shown. The optimum project duration (weeks) is
most nearly:
A. 10
B. 13
C. 16
D. 19
C. 16
A 5-story structure steel frame is to be
constructed. Story height is 12 ft. The maximum tolerance for out-of-plumbness of the columns (in.)
at the fourth floor is most nearly:
A. 0.25
B. 0.65
C. 0.95
D. 1.15
D. 1.15