Listing Flashcards
List shallow foundations.
Strip, pad and raft foundations. (Spread foundations)
List deep foundations.
Piles/columns.
What piles do low-rise and medium- to high-rise buildings use?
Low-rise:
-Short bored piles
Medium- to high- rise:
-Driven piles
-Driven cast-in-place concrete piles
-Bored piles
List types of pile tests.
Sonic test, pile load test, and standard penetration test (SPT).
List the criteria that the formation of building platforms by cutting (excavation) and filling must conform to.
Elevations, plan shapes, dimensions and falls.
List the major categories that fills can be divided into.
Control fills and random fills.
In control fills, what is prescribed and controlled during the working phase?
Constituents of the filling materials (types, mix, grading, and moisture content)
Means of compaction
Progress rate
Supervision
Field tests.
List the major types of retaining walls.
Gravity retaining walls
Cantilever retaining walls
and diaphragm retaining walls (commonly used for deep basement construction).
List the common forms of slope protection.
Rock facing
Gunite (Shotcrete)
Soil nails
Hydroseeding
What does the appropriate slope protection depend on?
Soil type(s) and conditions
Slope gradient
Location
Local climatic factors
List common examples of surface drains.
U-channels
Stepped channels
Catch pits
List the major types of excavation.
General excavation
Trench excavation
Deep excavation
Open cut excavation
List the functions that basements provide.
Extra rooms (like carpark, mechanical room and back-of-house)
Limit consolidation
Reduce differential settlement under buildings in which some parts are heavier than others
Exploit advantages of raft foundations
During and after basement construction, list the major functional requirements of basements.
Maintain the lateral thrust of mass of earth on the sides
Keep out water from the work
Provide mechanical ventilation and artificial lighting
Provide means of escape (MOE) in case of emergency (e.g. fire outbreak)
Provide fire compartmentation
Provide fire fighting measures
List what peripheral walls of a basement need to be able to do.
Resist overturning
Resist slide
Resist over-stressing in materials of the walls
In many cases, support vertical loads from the building above.
List the problems that deep excavation in urban areas present.
Presence of adjacent buildings, often old and fragile
Presence of streets or roads and underground services
Mechanical characteristics of the local subsoil
Lateral groundwater flow and level causing up-lift pressures (hydrostatic uplift) when groundwater table is higher than bottom of foundation level
List the types of temporary retaining structures.
Diaphragm wall (temporary or permanent)
Steel sheet piling
Soldier piles (aka Berlin method)
What is the construction process of diaphragm walls?
- Guide walls
- Trench excavation
- Stop ends and reinforcement cage
- Concreting
- Re-use of bentonite
- Ground anchors
List the methods that can be adopted to achieve watertight construction of basements.
Unlined concrete (integral waterproofing)
Lined construction with external tanking (external lining)
Lined construction with internal tanking (internal lining)
List the conventional construction materials for building structures.
Concrete
Formwork
Falsework
Reinforcement
Brickwork
List the materials used in the production of concrete.
Cement
Aggregate/sand
Water
List the commonly used aggregates.
Sand
Gravel
Crushed rocks
List the characteristics of concrete that are considered for engineering works.
Setting time (Initial and final)
Strength (7 day (65%) 28 day (99%))
Density (affected by types of aggregates used)
Workability (flowability and mouldability)
Resistance to sulphate (from subsoil) and/or acid (from rain) attack
List the potential hazards that green concrete must be protected from.
Excessive heat or cold
Excessive vibration
Excessive deflection/deformation
Excessive imposed loading
In normal weather conditions, list the minimum striking period of temporary formwork and falsework.
9 - 12 hours for column, walls and side of large beams
11 - 14 days for the soffit of slabs
15 - 21 days for the soffit of beams
28 days for cantilever beams or slabs
List the major categories that reinforcing bars can be broadly divided into.
Mild steel bars (aka round bars)
High yield bars (aka deformed/ribbed bars)
List the kind of bonds in brickwork laying.
Stretcher bond
English bond
Flemish bond
List the openings in solid walls.
Jambs
Heal
Sill
Lintel
List the ways that brickwork can be finished.
Joining (carried out as the work proceeds)
Pointing (carried out after completion)
Dowel bars
Brick meshes
Damp-proof courses