Limting Factor Analysis - 30% Flashcards

1
Q

What is a scares resource/ key factor / limiting factor ?

A

This is when a resource is running now

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Limiting factor steps

A
  1. Confirm limiting factory is NOT sales
    Calculate the shortfall of demand e.g labour hours
  2. Calculate the contribution per unit of scarce resource
    Unit contribution
    Labour hours per unit
    Contribution per labour hour
  3. Work out budgeted production and sales
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What to do when we is no scare resources

A

The relevant costs of the decisions are the differential costs between making & buying

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

With scares resources

A

If an organisation has to be subcontracted because of insufficient in- house resources, total costs are minimised if those units bought have the lowest extra variable cost of buying ( compared with making in - house ) per unit of scarce resource saved by buying.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Further considerations

A
  • how to use freed up capacity
  • whether using an outside supplier causes an industrial dispute
  • subcontractor reliability with delivery and production quality
  • Loss of flexibility and control by subcontracting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a fixed budget ?

A

These budgets are set for a single activity level. Master budgets are fixed budgets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a flexible budget ?

A

These are budgets which recognise different cost behaviours patterns, change as activity levels change.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How to prepare a flexible budget ?

A
  1. Decide whether costs are fixed, variable or semi- variable and split the semi variable costs using the high/low method or scatter graph method
  2. Calculate the budget cost allowance for each item = budgeted fixed cost + ( number of units x variable cost per unit )
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Using flexible budgets for control, what are the 3 steps

A
  1. Produce a flexed budget based on the actual activity level
  2. Compare the flexed budget with the fixed budget, and with actual results
  3. Identify the variances
    Volume variance = difference between fixed budget and flexed budget

Expenditure variance = difference between flexed budget and actual results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly