Level 3 Questions - Centrica Procurement, TRM & Tender Recommendation Flashcards

1
Q

How did you recommend a procurement route?

A

1) Produced a procurement report
2) Went through internal QA processes
3) Formally issued to client
4) Set up a call to go though

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What sections were included in your procurement report?

A

1) Introduction
2) Executive summary and recommendation
3) Key considerations
- project type
- client objectives
- market conditions
4) Procurement options
5) Forms of Contract
6) Market conditions
7) Conclusions and recommendation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why did you recommend a traditional form of procurement? Were there any disadvantages?

A

Based on the clients objectives of:

  • Cost certainty
  • Competitive tender procedure / value for money
  • Quality
  • Retention of responsibility of design team

Disadvantages:

  • No contractor input
  • Time / programme implication
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What other procurement routes were considered?

A

Single stage design and build

Achieve quality with:

  • Robust set of ERs
  • Novation of design team
  • Tendering at stage 3
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why was a single stage tendering procedure chosen?

A

As this enabled a competitive tender price to be received ensuring value for money

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What was the method / process of contractor selection?

A

Selective tendering

6 sent PQQs, 3 shortlisted for tender

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What documents were outlined in the responsibility matrix? Who was responsible for these?

A
  • ITT docs (Mace)
  • Preliminaries (Mace)
  • Pricing schedule (Mace)
  • Design information (Design team)
  • Programme (Client)
  • Pre construction information (PD)
  • Schedule of amendments (Client)

Matrix set out what was required by who, and set out a date by which the items need to be issued

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What were the sections included in your tender recommendation report?

A

1) Executive summary and recommendation
2) Tendering procedure
3) Tender price
4) Programme
5) Scoring matrix
6) Recommendation & next steps

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Once you had made your recommendation, what were the next steps you took?

A

Notify successful and unsuccessful contractors

Arrange a meeting with the successful contractor to agree contract sum

Contractor to issue construction phase plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why did you utilise a tender responsibility matrix? Could the PM not have managed programme?

A

As I was responsible for collating the tender documentation, part of my due diligence to ensure that I was issued all necessary documentation in good time

Ensured I kept track of what’s been issued / what’s still outstanding

Ensured I kept to timeframes I told my client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What happens if tenders are returned and are higher than cost plan, pre-tender estimate?

A

.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

I’m a very risk adverse client, what advice would you give me when it came to procurement?

A

Design and build is the most suitable as the design and cost risk is allocated to the contractor

Management forms of procurement are not suitable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What risks remain with me as a client when using D&B?

A

Quality, however this can be mitigated by:

  • Fully developed ERs
  • Appoint a clerk of works
  • Collateral warranties
  • Novate design team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

I have a project that I want to get on site quickly, what tender options would you recommend?

A
  • Two stage design and build

- Construction management / management contracting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What if I wanted cost certainty before starting on site?

What risk would this tendering option leave me open to?

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Your client is good friend with one of the tendering contractors, the contractor asks for an extension to the tender which your client is happy to give. What advice would you give?

A

If a tender extension has to be given there should be good reason to do so, and an extension should be given to all contractors to ensure fair tendering

17
Q

What are the key factors affecting procurement advice?

A

Client:

  • Experience
  • Type
  • Risk adverse?

Project objectives:
- Time, cost, quality, risk

Market conditions

18
Q

What would you advise your client if one tender price was significantly lower than the rest?

A

1) Analyse to understand why

2) Inform client of risks involved
- Is the contractor underpricing work to win as they are struggling financially?

  • Would this pose a risk to the client?
19
Q

What would you do if your tender returns were higher than your PTE?

A

.

20
Q

What was your tender recommendation based on? Were they the cheapest?

A

.