Level 2 Questions - King George's Gate Tender Process Flashcards

1
Q

What were the client’s key drivers?

A
  • Cost certainty
  • Start on site
  • Contractor involvement / buildability
  • Did not want to retain any cost / design risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why was a design and build route adopted?

A
  • Cost - Cost certainty
  • Time - earlier start on site
  • Contractor involvement - engaged early to help with programming, buildability and construction methodology
  • Risk - risk allocated to contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why was a single stage procedure adopted?

A
  • Competitive returns to ensure value for money

- tbc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why wasn’t a 2 stage adopted?

A

tbc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What other procurement routes could have been considered?

A
  • Single stage traditional procurement
  • Two stage design and build
  • Management contracting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If time was a key driver why wasn’t negotiation adopted?

A

Negotiation wouldn’t have achieved a competitive price and ensured value for money

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How were the contractors selected?

A

Selected from a framework

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How many contractors did you issue a PQQ to?

A

Issued to 10 contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What was the scoring criteria of the PQQ?

A

PQQ scoring criteria was:

  • Pass / fail sections - financials and H&S
  • Relevant experience - 70%
  • Overall quality of submission - 30%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How was the pre-qualification results assessed?

A

The results were assessed collaboratively

  • Financials - client
  • Quality questions - client, PM, QS
  • H&S questions - Principal designer

A scoring matrix was used to analyse the qualitative sections

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How many contractors were shortlisted after the PQQ process?

A

3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What tender documents were issued to the contractors?

A
Invitation to tender letter 
Form of tender 
Bona fide tender certificate 
Instructions to tenderers
Schedule of contract amendments
Tender Query Sheet
Preliminaries 
Employers Requirements 
Pre-construction information 
Contract Sum Analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What was the method of issuing the tender packs?

A

Online E-tendering (managed internally by the client)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How long was allowed for the tender period?

A

6 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Were there any addendums during the tender process?

A

Yes, a total of 6 addendums

Mainly consisting of updated design information and surveys

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Were there many pre-tender queries raised?

A

Yes, there were a total of XX

Mainly consisting of…..

17
Q

Why weren’t mid-tender interviews carried out?

A

The client confirmed that they did not wish to have mid-tender interviews and instead set up post-tender interviews

18
Q

Were there any tender withdrawals? How did you deal with these?

A

No, however if there were I would ensure that I followed the clients process for any tender withdrawals

19
Q

How did you go about completing the tender opening form? What was included?

A
  • I set up a tender opening meeting and invited the client and project team
  • I ensured there was another professionally qualified person there to witness the opening
  • The tender opening form included:
    • Tender price
    • Programme
    • Alternative tender submissions
    • Comments

Once it was completed it was signed and dated by all parties present

20
Q

How did the PTE compare to the tender returns?

A
  • PTE value - £55m

- Tender returns ranged from £52m to £54m (within 5%)

21
Q

Were there any errors picked up in the tender analysis? How were these dealt with?

A

TBC with dan

Alternative 2 allowing the contractors to correct their error

22
Q

How many post tender queries were sent? What main items were covered here?

23
Q

What was the scoring criteria when assessing the tender returns?

24
Q

What was the format of the post tender interviews?

25
What was the scoring criteria when assessing the tender returns?
1) Compliant bid - pass / fail 2) Health and Safety - 10% 3) Programme .... tbc
26
How did you go about producing the preliminaries document on King George's Gate?
- Used NBS software - Used the pre-construction information and any relevant information as the basis of filling out key parts of preliminaries - Produced a clarification schedule and issued a set of queries to the client & project team in order to retrieve the relevant info to fill out prelims - Once completed I issued as a draft to the client before formalising and including in tender pack
27
How were tender addendums and pre / post tender queries issued on King George's Gate
tbc
28
What was the sections included within the tender report?
- Executive summary and recommendation - Tender procedure - Tender compliance - Tender pricing - Remaining risks / outstanding qualifications - Qualitative scoring - Recommendation and next steps
29
Were there any remaining risks you outlined in the tender recommendation report?
I outlined some remaining risks which sat with the client, including: - Contract amendments and conditions - Third party agreements - Client changes - Works near the railway - Underground obstructions - Disposal of hazardous materials (non-hazardous allowed for)
30
How did you inform unsuccessful contractors that they did not win the work? What information was sent to them?
Issued a letter explaining that they were unsuccessful Present the evaluation criteria and their scores against this criteria Reasons for the criteria above