Level 2 Questions - King George's Gate Tender Process Flashcards
What were the client’s key drivers?
- Cost certainty
- Start on site
- Contractor involvement / buildability
- Did not want to retain any cost / design risk
Why was a design and build route adopted?
- Cost - Cost certainty
- Time - earlier start on site
- Contractor involvement - engaged early to help with programming, buildability and construction methodology
- Risk - risk allocated to contractor
Why was a single stage procedure adopted?
- Competitive returns to ensure value for money
- tbc
Why wasn’t a 2 stage adopted?
tbc
What other procurement routes could have been considered?
- Single stage traditional procurement
- Two stage design and build
- Management contracting
If time was a key driver why wasn’t negotiation adopted?
Negotiation wouldn’t have achieved a competitive price and ensured value for money
How were the contractors selected?
Selected from a framework
How many contractors did you issue a PQQ to?
Issued to 10 contractors
What was the scoring criteria of the PQQ?
PQQ scoring criteria was:
- Pass / fail sections - financials and H&S
- Relevant experience - 70%
- Overall quality of submission - 30%
How was the pre-qualification results assessed?
The results were assessed collaboratively
- Financials - client
- Quality questions - client, PM, QS
- H&S questions - Principal designer
A scoring matrix was used to analyse the qualitative sections
How many contractors were shortlisted after the PQQ process?
3
What tender documents were issued to the contractors?
Invitation to tender letter Form of tender Bona fide tender certificate Instructions to tenderers Schedule of contract amendments Tender Query Sheet Preliminaries Employers Requirements Pre-construction information Contract Sum Analysis
What was the method of issuing the tender packs?
Online E-tendering (managed internally by the client)
How long was allowed for the tender period?
6 weeks
Were there any addendums during the tender process?
Yes, a total of 6 addendums
Mainly consisting of updated design information and surveys