Level 2 - Development Appraisals Flashcards

1
Q

T1. Tell me about a development appraisal which you have been involved with and how you undertook the work?

A

..

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

T2. Do you calculate your costs for a development appraisal on a GIA basis or GEA basis?

A

I calculate them on a GIA basis. Residential dwellings are measured on a GIA basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

T3. How do you work out your contingency rate?

A

Typically a contingency rate would be between 5-10% of the construction costs but this would depend on the level of risk of the development.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

T4. What is contingency?

A

A future event or circumstance that cannot be predicted with certainty, i.e. additional construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

T5. How would you calculate the Gross Development Value of a new residential development?

A

The GDV of a new development can be obtained gaining evidence of recent sales transactions within the near vicinity, and also be obtained from market evidence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

T6. How would you reflect planning requirements in your development appraisal?

A

If I was undertaking a residential appraisal I would take into account an appropriate level of s.106 and s.278 costs, that I would find out about from the relevant planning authority, and this would be deducted from the GDV after accounting for construction costs, and a contingency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

T7. How do you estimate the total construction cost for a scheme?

A

In order to assess the construction cost of a scheme, I would look to use the BCIS, to ascertain what cost levels are on nearby schemes in the area. I would check this level against what local Quantity surveyors felt was an appropriate level of costs to account for.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

T8. Where would you typically get your finance rate for a development appraisal from?

A

Firstly check with your client as they may have a specific loan facility and be able to borrow money at a certain rate, I would then use that.

I would also look at comparable scheme to see what finance rate had been used. However the best way of working out the best level of finance achievable for the scheme would be to talk to the developer, and find out what finance arrangements he has been able to find on recent projects, and compare the market conditions then with the current market.

A typical market finance rate would be 6%.

Interest should also be calculated to cover the time period from the purchase of the land, the construction of the building and any projected letting / sale void upon completion of construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

T9. If I was Joe Bloggs carrying out a development, would the finance rate be higher or lower than more regular finance users?

A

It would be higher

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

T10. Outline the main focus of development finance used by developers?

A

Debt and Equity funding

Debt funding is lending money from a bank or other financial institution.

Equity funding is selling shares in a company, JV’s or using your own money.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

T11. What is a typical LTV ratio?

A

Crest Nicholson was self funded. However talking to colleagues at other organisations typically 50% - 60%. It used to go up towards 70% but lenders are now more risk adverse.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

T12. When do you need most of your costs for a development? What is an S -Curve?

A

Typically developers do not need access to all the capital at once due to the S Curve nature of costs within a development scheme, that allow for costs to start at a low level, and rise through the construction process.

The interest on the finance will normally be on a rolled up, compound interest basis, that will provide for the full amount of financing needed throughout the development.

As not all of the money will not need to be drawn down on at once the interest rate payable will start low and will increase with the more borrowing. During site preliminaries there aren’t many outgoing costs and therefore your borrowing will be low. As time progresses into the construction phase your costs will increase particularly when the frame of your building is being put up etc. This may mean that the increase in borrowing is quite steep. Once your development is near complete and it is just the marketing your costs of finance will the tail off until you have sold your development and paid off your loan.

You would typically look at it that you would only need to pay full interest for half of the proposed development, as interest payments will be very low and the start and then will be high in the second half. It in theory evens itself out!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

T13. You mention that you carried out a development appraisal of a development site in Wokingham (West Court) Talk me through this?

A

REVIEW ASAP, INCORPORATE.

I recently purchased a site in Shoreham, which had outline consent for 106 residential units. I was instructed to lead the planning application for the reserved matters application.

The scheme had been costed and I reviewed the likely GDV for the scheme. I looked at recent comparable residential sales around the area.

• Site – 5.41 gross acres

  • GDV (Rent * Yield)
  • Less purchasers costs = NDV (these are the costs a purchaser will need to pay when buying the site from you!)
  • Subtract Site Costs – They already owned the site – price £5,000,000.
  • Subtract Total costs – planning, S106, professional fees including structural engineers, CDM contractor, M&E consultants 10% - 15% - c. £150 psf
  • Demolition - £1,500,000.
  • Subtract Contingency – 5% of total construction costs.
  • Subtract Marketing costs - £740,000
  • Less Finance Costs – 6%. I confirmed the finance costs with my line manager.
  • Profit on GDV of 26%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

T14. Outline the differences between a residual valuation and a development appraisal.

A

A development appraisal will typically give you the profitability of a proposed development and a residual valuation will give you the value of the land.

A residual will give you the Market Value and therefore you would need to use market led costs, either from the BCIS website or if your client has a tendered scheme where they have gone to the market to actively obtained costs.

A residual is based on the valuer’s inputs and is for a practical purpose.

A development appraisal will be on costs provided by your client. You are able to play around with the costs to achieve your desired profit levels.

Development appraisal is usually based on the clients inputs. Give you a calculation of worth.

Residual Valuation is a valuation of a property holding, it is a specific calculation to establish the residual value of a development site, by estimating the GDV of a proposed scheme, deducting the total proposed development costs to arrive at a MV of the development site.

This valuation assumes a number of key variables and is undertaken at a particular point in time, using current costs and values.

It can be used to establish the site value or profitability of a proposed development scheme.

Development Appraisal
Is a calculation (or series of) to establish the viability of a proposed development.

It does not produce a Market Value but provides guidance as to whether the proposed development is commercially viable.

It can establish the land value and / or the likely profit to be generated by the proposed development

This can be in the form of a traditional residual valuation approach or using a DCF method of valuation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

T15. 15. Have you carried out a residual valuation?

A
  • Yes I assisted with a residual valuation of a site in Chertsey.
  • They submitted a planning application for a proposal of 130 units.
  • Comp evidence to find out the GDV.
  • I took off costs which I obtained from the quantity surveyors. £65.00 psf sq ft build costs.
  • I used a finance rate of 6.00% which was approved by the client.
  • Took off profit on GDV of 25%.
  • Site value of £1.21m per acre.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

T16. 16. How do you calculate the finance costs for a residual valuation?

A

Site purchase – straight line over entire period

Total Construction Costs & associated – S curve ½ interest rate

Holding – until disposal (empty rates, service charge & interest charges)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

T17. What factors affect the sensitivity of an appraisal? How can you deal with these sensitivities? And what is a sensitivity analysis?

A

Development Appraisals are sensitive to many factors, particularly to the variables that are put into the appraisal, such as construction costs, rates of interest, the yield and the rent.

A sensitivity analysis will show you how the outcome changes when the inputs are varied slightly.

Will provide different scenarios to the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

T18. What software does your practice use for development appraisals? Do you like this software? What are its limitations?

A

I don’t undertake Development Appraisals at Hadron Consulting. Crest Nicholson used Excel Spreadhseets to undertake development appraisals, which whilst being a useful tool, the key assumptions and calculations remain hidden, and therefore the user is reliant on the information being put in being correct. I do like the software now, as I am aware of how to use it, and am practised at it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

T19. Tell me about an instruction which you have dealt in respect of undertaking a form of sensitivity analysis. What are the main forms of sensitivity analyses?

A

I undertook a development appraisal of a development proposal for a site in Sayers Common. I ran various sensitivity analyses, changing the GDV and potential costs.

There are 3 forms of sensitivity analysis which can be used to consider the accuracy of the valuation;

1) Simple Sensitivity Analysis – a series of sensitivity analysis should be run to consider the impact of changes of fixed amounts to the key variables, such as construction costs, rates of interest and the GDV.
2) Scenario Analysis – the valuer can consider what might happen to the key variables in a scheme under differing economic conditions, such as changes in interest rates or rental growth rates on a pessimistic and optimistic basis. This technique can be enhanced by adopting probability linked scenario analysis, by adopting the assessment of probabilities to the variables.
3) Simulation – Crystal Ball / Monte Carlo. Require the probable value for each variable to be identified, for probability to be assumed to each and then for random numbers to be generated in order for the value to be used in the calculation to be selected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

T20. What are the main weaknesses of the residual method of valuation?

A

There are 4 main areas of weakness;

1) Development appraisals / residual valuations are unstable and extremely sensitive to minor adjustments.
2) The method does not take into account the timing of cash flows (unlike the DCF approach). It is growth IMPLICIT rather than growth explicit.
3) High quality of information for the inputs is essential
4) IMPLICIT assumptions remain hidden
5) Always cross check with comparable sites if possible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

T21. Why are purchaser’s costs deducted from an appraisal and when are they deducted?

A

Purchasers costs are deduced from the GDV as a purchaser would need to pay these when buying the finished product. This will give you the NDV.

Costs will need to be put in place if you wanted to buy the land. Agents costs, legal costs and Stamp Duty on buying the land.

1.5% costs will need to be taken off at the end as these are costs to the Developer when he needs to sell the site. 1.5% of the NDV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

T22. How do you reflect potential contamination costs in the valuation of a brown field site?

A

I would reflect potential contamination in a brownfield site by either talking to an expert in this field and getting an estimate for the costs of remediation, otherwise the additional costs of remediation could be reflected in the contingency level put on the construction costs. It may also be appropriate in some case to reflect the additional risk associated with the remediation within the ARY.

You may put in a cost obtained from a specialist into you appraisal for remediation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

T23. What are the advantages of using a DCF calculation for the valuation of a development site rather than a residual valuation?

A
  • Allows for the valuer to input any changes in costs or values over the project.
  • It shows the timing of peak cash outlays
  • Shows outstanding debt at any given point
  • Accounts or phasing over the build period that must be reflected in the land value
  • Allows for sensitivity analysis to examine the effect of input changes on the outputs.
  • Allows for off plan sales to be factored in.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

T24. 24. What is a s.106 agreement? How do you have regard to it in your valuation of a development site?

A
  • S.106 contribution could include the funding of the construction of a new local school or community centre, other infrastructure or the provision of social housing.
  • It should be incorporated into the Total Building Cost or if in a cash flow paid at the commencement of construction.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

T25. What are the likely costs of construction of?

A

I would consult a BCIS / Quantity surveyor but…
• Residential - £130-£150 psf base cost. (RC FRAME/SOUTH EAST)

  • Office - £150-£200 psf but have had no experience
  • Industrial warehouse - £35 – 45 psf but have had no experience
  • Industrial estate - £50 - £60 psf but have had no experience
  • Retail shop - £80 - £90 psf but have had no experience
26
Q

T26. How could the risk element to the developer’s profit be reduced?

A

Pre-let scheme or forward funding or forward commitment.

27
Q

T27. What are the signs of contamination and how would you account for the existence of contamination whilst determining the value of a development site?

A

Signs of contamination to look out for, Evidence of current use of chemicals, oils, solvents, subsidence, signs of mining etc.

The valuation report, can make the assumption that no enquiries regarding contamination or other hazards have been undertaken but if a problem is suspected the valuer should recommend further investigation. Also look for environmental reports on the property and refer to this in the report. State assumption - in line with RICS Red Book.

28
Q

T28. How large an office property or industrial unit could you construct on a 1 acre development site?

A

Would be assessed on a case by case basis.

It would totally depend where it is. In central London, 90% - 100% site cover. If the office was in the regions and needed a lot of car parking, maybe 50% - 60%.

Industrial warehouse needs a large yard so 40% is typical. An industrial estate would need a lot less yard so maybe 60%.

29
Q

T29. What is the normal car parking ratio required by local planning authorities for such use? How do you find out what standard is required?

A

It would differ for different locations. I would check on the planning website and speak to local agents. Maybe in the regions 1:250, but in a town 1:1000 maybe.

Would look up on the Local Plan.

30
Q

T30. Tell me about the planning process generally in relation to the development of a site? What is the statutory framework?

A

A planning application would be submitted for a proposed scheme. Setting out exactly what the scheme is, the use class, size etc.

A change of use requires a full planning application, which necessitates all details of the planning proposal, including floor plans, site layout together with supporting information. But consult the local plan to view policies against which planning applications for development will be judged against.

31
Q

T31. Why should you take into account the cost of a CDM co-ordinator when undertaking a residual valuation?

A

In line with Construction and Design Management (CDM) Regualtions 2007 – Updated in 2015
Which requires H&S during the design and management of all commercial building projects

32
Q

T32. How is social housing valued in a residual valuation of a residential site? What is social housing and what are the statutory provision requirements in your area?

A

I do not have any experience in social housing. I would therefore consult a colleague who did or contact the planning authority for the area in which my development site was.

Social house I believe is similar to council housing as opposed to affordable housing.

33
Q

T33. What is affordable housing? What impact does it have on the viability of a development scheme?

A

A certain proportion of affordable housing maybe required as part of your development if you are doing a residential scheme.

34
Q

T34. What is a collateral warranty?

A

It will provide a tenant or a new owner with a direct link to the developer or whoever carried out the works by privity of contract. i.e. if there is anything wrong with the construction they can go after them to claim for damages.

35
Q

T35. What is an environmental impact assessment and when is it required and by whom?

A

Looks into the environmental impact of a development, carried out by local authority and is required at the planning stage. It would take into account increases in cars and noise pollution and the impact that the development will have on the environment and economic impact.

36
Q

T36. What is something that is recent in development? Is this a good thing?

A

The permitted right to change of use from offices to residential as at May 2013 without planning permission.

I think it will help with the housing shortage, however I believe that there is also a lack of supply of good quality in offices in core locations and these are the likely targets due to the higher use value in residential that developers will target.

37
Q

T37. What are the other planning implications you might have to consider?

A
  • Section 106 (TCP Act 1990)
  • Community Infrastructure Levy (Planning Act 2008)
  • Section 278 (Highways Act 1980)
  • Planning permission
38
Q

T38. How much are professional fees typically?

A

Professional fees typically include CDM, M&E consultants, structural engineers etc. – 10% - 15% of construction costs.

39
Q

T39. Would you need an EPC?

A

Yes you would with any completed development before it is marketed. This cost will have to be taken into consideration

40
Q

T40. How did you work out your marketing costs?

A

Crest Nicholson have a consistent 5/3,5% on all developments.

41
Q

T41. How much would architects costs be?

A

Maybe 1% or 2% of the construction costs. Depends on the complexity of the development.

42
Q

T42. How would you work out the construction period?

A

Speak to my development colleagues or Building surveyors. Look at comparable schemes.

43
Q

T43. Talk me through the Circle Developer Screen?

A

Labels at the top – Project, Definition, Cash Flow, Summary, Data Checker
• Project you can input the details of the property, address etc.
• Definition – you can input your various construction costs, fees, areas, rents, yield etc, marketing costs, land acquisition.
• Project Cash flow – shows your cash flow of the proposed development
• You can make assumptions via the assumption tab.
• You can ass in any finance costs in the finance tab
• You can add in timescales for the development in the timescales tab.
• Capitalised areas will give you the screen to put in most of your inputs i.e. size, rent, yield etc.

44
Q

T44. Can you come up with a land value on a development appraisal?

A

Yes you can

45
Q

T45. Can you come up with a land value on a development appraisal?

A

Costs are less likely to vary, where as a small shift in the yield may make the outcome vary substantially.

46
Q

T46. What is profit erosion?

A

It is the time it takes for a developer’s profit to be wiped out by the holding costs post construction.

47
Q

T47. Are conversion costs different to construction costs?

A

Yes, they are typically higher than normal build costs.

48
Q

T48. 48. Would a developers profit be higher if they didn’t have planning permission?

A

Yes, as there would be more risk involved.

49
Q

T49. What would you look for when on inspection?

A
  • Contamination
  • Access
  • Topography of the site – whether it needs levelling
  • TPO’s
  • History of site
  • Flood risk
  • Existing buildings
  • Leases inside of the Act
  • Neighbouring properties
  • Rights of Way
  • Easements
50
Q

T50. What is Valuation Information Paper 12 (2008) - the Valuation of Development Land?

A

The aim of the information paper is to assist the valuer in the more complex cases by providing a framework which a consistent approach to the valuation of development land is adopted. It does not advise the valuer how to undertake the valuation – this is a matter of professional expertise – but, by following the principles, the valuer may have confidence that the significant factors relevant to this type of valuation have been considered.

  • It covers the whole process including the facts about the site (site inspection, gathering site information, establishing the planning potential and the environmental due diligence).
  • The judge of certainty of the valuation and the process involved it is essential that the valuer has an awareness of the characteristics of the existing site.
  • The level of information is determined by the stage at which the valuation is being prepared – i.e. planning process, potential acquisition of land, at the valuation date when the redevelopment has commenced.
51
Q

K1. What are the three main approaches to valuing development land?

A

Comparison with the sale price of land for similar comparable development, assessment of scheme and residual method to derive value, and the discounted cash flow method.

52
Q

K2. When visiting a site, what safety precautions would you take?

A

..

53
Q

K3. Name site specific issues you would look for on-site which would affect the development?

A

.Extent of the site, boundary features, relation to neighbouring properties, topography, rights of way/easements/overhead power lines/water courses etc, access, constraints…

54
Q

K4. How would you assess the planning background of a site?

A

The planning history should be available on the LPA website, including documents of recent applications. The proposals map and planning policy would give any designations over a site. If a site has been promoted, there may be a site assessment in the SHLAA. If there are no designations, a site has not been promoted and there is no relevant planning history, local Planning Policy and how the area performs in terms of meeting its 5 year housing land supply would indicate the requirement for further housing land.

55
Q

K5. What costs are deductible from the GDV when using the residual method of valuation?

A
  • Cost of construction/contingency of around 5% dependent on risk
  • Professional fees, generally around 10%
  • Cost of finance, generally between 5-7%
  • (Cost of sale/agents fees, holding costs, overage payments, SDLT etc)
56
Q

K6. How is risk demonstrated in a financial appraisal?

A

Risk is reflected in the target profit margin, or in the case of an investment property, in the rental yield…. Is this correct?

57
Q

K7. What is IRR?

A

The Internal Rate of Return is the interest rate that makes the Net Present Value zero.
PV = FV / (1+r)n
• PV is Present Value
• FV is Future Value
• r is the interest rate (as a decimal, so 0.10, not 10%)
• n is the number of years
The internal rate of return is simply the rate of return on an investment. IRR is similar to the net present value calculation. The NPV calculation finds the net present value using a predefined discount rate. IRR finds the discount rate that makes the NPV equal to zero. The discount rate is the cost of borrowing or using money for investments. The decision to accept or reject the purchase depends on the whether the internal rate of return is higher than the discount rate. The decision criteria for these projects is simple, accept the project if the IRR is higher than the discount rate or the cost of borrowing.

58
Q

K8. What is ROCE?

A

Return on Capital Employed. A financial ratio that measures a company’s profitability and the efficiency with which its capital is employed. Return on Capital Employed (ROCE) is calculated as:
ROCE = Earnings Before Interest and Tax (EBIT) / Capital Employed

59
Q

K9. What is GDV?

A

Gross development value.

60
Q

K10. What are the 5 methods of valuation?

A

In the UK, valuation methodology has traditionally been classified into five methods:
1. Comparable method.
Used for most types of property where there is good evidence of previous sales.

  1. Investment/income method.
    Used for most commercial (and residential) property that is producing future cash flows through the letting of the property. If the current Estimated Rental Value (ERV) and the passing income are known, as well as the market-determined equivalent yield, then the property value can be determined by means of a simple model.
  2. Accounts/profits method.
    Used for trading properties where evidence of rates is slight, such as hotels, restaurants and old-age homes. A three-year average of operating income (derived from the profit and loss or income statement) is capitalised using an appropriate yield. Note that since the variables used are inherent to the property and are not market-derived, therefore unless appropriate adjustments are made, the resulting value will be Value-in-Use or Investment Value, not Market Value.

. Development/residual method.
Used for properties ripe for development or redevelopment or for bare land only.

  1. Contractor’s/cost method.
    Used for only those properties not bought and sold on the market.